  "releaseId": "2026-09-22-preview-9",
  "previousReleaseId": "2026-09-22-preview-8",
  "publishedAt": "2026-09-22",
  "note": "Changes between dated publications. New or revised evidence can change an observation without indicating a physical change at the facility. Before and after values are retained for citation.",
  "facilities": [
    {
      "id": "airtrunk-syd2",
      "change": "updated",
      "fields": [
        "stages",
        "certification",
        "sourceIds",
        "notes",
        "aliases"
      ],
      "before": {
        "stages": [
          {
            "asOf": "2024-08-29",
            "mwQualifier": "reported",
            "stage": "operating",
            "mw": 30,
            "mwBasis": "IT",
            "scopeId": "airtrunk-syd2-phase-three",
            "sourceIds": [
              "review-airtrunk-syd2-phase3-complete-20260922",
              "review-airtrunk-syd2-phase3-it-20260922"
            ],
            "note": "Only the third-phase 30 MW increment is evidenced here. AirTrunk confirms completion; contemporaneous DCD reporting explicitly identifies the same expansion as IT capacity. Neither source establishes that the whole 120+ MW campus was fitted out.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          },
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "operating",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "airtrunk-syd2-other-operating-phases",
            "sourceIds": [
              "review-airtrunk-syd2-phase3-complete-20260922",
              "review-airtrunk-syd2-profile-20260922"
            ],
            "note": "Earlier operating phases exist, but their separately commissioned IT total remains unquantified in this evidence.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "certification": {
          "status": "strategic-facility",
          "scope": "AirTrunk Australia, SYD2: only the named Certified Strategic facility. This does not certify other buildings or the whole parent campus.",
          "sourceIds": [
            "review-hcf-register-20260922"
          ]
        },
        "sourceIds": [
          "cov-airtrunk-story",
          "cov-airtrunk-mel2-announcement",
          "dcm-9647",
          "hcf-register",
          "natural-earth-cities",
          "review-hcf-register-20260922",
          "review-airtrunk-syd2-phase3-complete-20260922",
          "review-airtrunk-syd2-phase3-it-20260922",
          "review-airtrunk-syd2-profile-20260922"
        ],
        "notes": [
          "Map location, when supplied, represents the city rather than a verified facility coordinate.",
          "Do not add Datacom's colocation service within this campus as another physical data centre.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "Directory reconciliation: The public publisher withholds exact location. This match uses named identity only and does not use hidden embedded coordinates or addresses.",
          "The accepted 30 MW is one completed phase, not total campus capacity. The operator used its 120 MW campus headline while this phase was still under construction in November 2023."
        ],
        "aliases": null
      },
      "after": {
        "stages": [
          {
            "asOf": "2024-08-29",
            "mwQualifier": "reported",
            "stage": "operating",
            "mw": 30,
            "mwBasis": "IT",
            "scopeId": "airtrunk-syd2-phase-three",
            "sourceIds": [
              "review-airtrunk-syd2-phase3-complete-20260922",
              "review-airtrunk-syd2-phase3-it-20260922"
            ],
            "note": "Only the third-phase 30 MW increment is evidenced here. AirTrunk confirms completion; contemporaneous DCD reporting explicitly identifies the same expansion as IT capacity. Neither source establishes that the whole 120+ MW campus was fitted out.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          },
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "operating",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "airtrunk-syd2-other-operating-phases",
            "sourceIds": [
              "review-airtrunk-syd2-phase3-complete-20260922",
              "review-airtrunk-syd2-profile-20260922"
            ],
            "note": "Earlier operating phases exist, but their separately commissioned IT total remains unquantified in this evidence.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          },
          {
            "asOf": "2025-10-09",
            "mwQualifier": "maximum",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "airtrunk-syd2-apollo-approved-extension",
            "mw": 45,
            "mwBasis": "unknown",
            "sourceIds": [
              "abc-airtrunk-apollo-planning-20260922",
              "abc-airtrunk-apollo-relationship-202505"
            ],
            "note": "Approved adjoining Apollo Place extension. The 45 MW approval has no separately verified IT allocation; it remains outside IT subtotals. Its relationship to the operator whole-campus headline is unresolved.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "certification": {
          "status": "strategic-facility",
          "scope": "AirTrunk Australia, SYD2: only the named Certified Strategic facility. This does not certify other buildings or the whole parent campus. The adjoining Apollo Place extension has no separately verified certification scope.",
          "sourceIds": [
            "review-hcf-register-20260922"
          ]
        },
        "sourceIds": [
          "cov-airtrunk-story",
          "cov-airtrunk-mel2-announcement",
          "dcm-9647",
          "hcf-register",
          "natural-earth-cities",
          "review-hcf-register-20260922",
          "review-airtrunk-syd2-phase3-complete-20260922",
          "review-airtrunk-syd2-phase3-it-20260922",
          "review-airtrunk-syd2-profile-20260922",
          "abc-airtrunk-apollo-planning-20260922",
          "abc-airtrunk-apollo-relationship-202505"
        ],
        "notes": [
          "Map location, when supplied, represents the city rather than a verified facility coordinate.",
          "Do not add Datacom's colocation service within this campus as another physical data centre.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "Directory reconciliation: The public publisher withholds exact location. This match uses named identity only and does not use hidden embedded coordinates or addresses.",
          "The accepted 30 MW is one completed phase, not total campus capacity. The operator used its 120 MW campus headline while this phase was still under construction in November 2023.",
          "The adjacent Apollo Place development is approved under SSD-67407231 and linked to the existing 1 Sirius Road site. No separate physical campus or certification scope is inferred."
        ],
        "aliases": [
          "Apollo Place Data Centre"
        ]
      }
    },
    {
      "id": "dci-canberra-01",
      "change": "updated",
      "fields": [
        "stages",
        "sourceIds",
        "notes",
        "fieldReviews",
        "aliases",
        "address"
      ],
      "before": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "planned",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "dci-canberra-01-planned",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown",
            "sourceIds": [
              "cov-dci-locations"
            ],
            "note": "Development is identified in the Poplars Innovation Precinct at Jerrabomberra. Physical construction has not been verified."
          }
        ],
        "sourceIds": [
          "cov-dci-locations",
          "dcm-11352",
          "natural-earth-cities"
        ],
        "notes": [
          "Map location, when supplied, represents the city rather than a verified facility coordinate.",
          "Canberra market location; Jerrabomberra is in NSW, not the ACT.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations."
        ],
        "fieldReviews": [],
        "aliases": null,
        "address": null
      },
      "after": {
        "stages": [
          {
            "asOf": "2025-11-06",
            "mwQualifier": "maximum",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "dci-canberra-01-approved-it-design",
            "mw": 20,
            "mwBasis": "IT",
            "sourceIds": [
              "abc-poplars-final-assessment-20251106",
              "abc-poplars-cbr01-identity-20250120"
            ],
            "note": "Approved design comprises Stage 1 at 8 MW IT, Stage 2 at 4 MW IT and Stage 3 at 8 MW IT. These sum to 20 MW IT within 25.4 MW total facility power. Construction commencement and commissioning dates are unverified.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "sourceIds": [
          "cov-dci-locations",
          "dcm-11352",
          "natural-earth-cities",
          "abc-poplars-final-assessment-20251106",
          "abc-poplars-cbr01-identity-20250120"
        ],
        "notes": [
          "Map location, when supplied, represents the city rather than a verified facility coordinate.",
          "Canberra market location; Jerrabomberra is in NSW, not the ACT.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "Approved 6 November 2025. CBR01 in primary documents and CBR02 / Poplars in the ABC table refer to the same project; they are not separate sites."
        ],
        "fieldReviews": [
          {
            "field": "capacity",
            "outcome": "verified",
            "sourceIds": [
              "abc-poplars-final-assessment-20251106",
              "abc-poplars-cbr01-identity-20250120"
            ],
            "note": "Final assessment allocates 8 + 4 + 8 MW IT across the three stages; count the 20 MW design once.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "address",
            "outcome": "verified",
            "sourceIds": [
              "abc-poplars-final-assessment-20251106",
              "abc-poplars-cbr01-identity-20250120"
            ],
            "note": "The named project is at 2 Wolseley Place, Jerrabomberra NSW. Precise coordinates remain unverified.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "identity",
            "outcome": "verified",
            "sourceIds": [
              "abc-poplars-final-assessment-20251106",
              "abc-poplars-cbr01-identity-20250120"
            ],
            "note": "Planning documents call this CBR01 at Poplars. ABC labels it CBR02; both descriptions refer to this same street-address project.",
            "checkedOn": "2026-09-22"
          }
        ],
        "aliases": [
          "DCI Poplars Data Centre",
          "CBR02 / Poplars (ABC label)",
          "SSD-64287712"
        ],
        "address": {
          "street": "2 Wolseley Place",
          "locality": "Jerrabomberra",
          "region": "New South Wales",
          "postalCode": "",
          "country": "AU",
          "sourceIds": [
            "abc-poplars-final-assessment-20251106",
            "abc-poplars-cbr01-identity-20250120"
          ],
          "verifiedOn": "2026-09-22"
        }
      }
    },
    {
      "id": "dcm-10727",
      "change": "updated",
      "fields": [
        "stages",
        "sourceIds",
        "notes",
        "aliases",
        "address",
        "fieldReviews"
      ],
      "before": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "unknown",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "dcm-10727-unverified",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown",
            "sourceIds": [
              "dcm-10727"
            ],
            "note": "This directory listing does not establish a current commissioned lifecycle. Technical figures remain directory-reported observations, outside capacity totals."
          }
        ],
        "sourceIds": [
          "dcm-10727",
          "natural-earth-cities"
        ],
        "notes": [
          "Added from a public Data Center Map listing. Identity, technical specifications and location remain directory-reported until corroborated against operator or planning evidence."
        ],
        "aliases": null,
        "address": null,
        "fieldReviews": null
      },
      "after": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "unknown",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "dcm-10727-unverified",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown",
            "sourceIds": [
              "dcm-10727"
            ],
            "note": "This directory listing does not establish a current commissioned lifecycle. Technical figures remain directory-reported observations, outside capacity totals."
          },
          {
            "asOf": "2024-04-05",
            "mwQualifier": "reported",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "aws-eastern-creek-echidna-approved-development",
            "mw": 35,
            "mwBasis": "unknown",
            "sourceIds": [
              "abc-echidna-planning-20260922"
            ],
            "note": "The portal describes an approved 35 MW development at the existing site. IT versus total electrical basis and current construction progress are unverified. This is not evidence that every existing building shares the proposed lifecycle.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "sourceIds": [
          "dcm-10727",
          "natural-earth-cities",
          "abc-echidna-planning-20260922",
          "abc-echidna-address-20230705"
        ],
        "notes": [
          "Added from a public Data Center Map listing. Identity, technical specifications and location remain directory-reported until corroborated against operator or planning evidence.",
          "Project Echidna SSD-47320208 is approved at 10 Eastern Creek Drive. The same address appears in the existing AWS Eastern Creek directory profile.",
          "The portal describes 35 MW; ABC reports 35.2 MW. Neither figure is accepted as IT capacity here. Earlier development at this address requires separate building and phase reconciliation."
        ],
        "aliases": [
          "Project Echidna",
          "SSD-47320208"
        ],
        "address": {
          "street": "10 Eastern Creek Drive",
          "locality": "Eastern Creek",
          "region": "New South Wales",
          "postalCode": "",
          "country": "AU",
          "sourceIds": [
            "abc-echidna-address-20230705"
          ],
          "verifiedOn": "2026-09-22"
        },
        "fieldReviews": [
          {
            "field": "address",
            "outcome": "verified",
            "sourceIds": [
              "abc-echidna-address-20230705"
            ],
            "note": "Council identifies the project at 10 Eastern Creek Drive. Precise coordinates remain unverified.",
            "checkedOn": "2026-09-22"
          }
        ]
      }
    },
    {
      "id": "dcm-19094",
      "change": "updated",
      "fields": [
        "name",
        "stages",
        "evidenceStatus",
        "sourceIds",
        "notes",
        "aliases",
        "address",
        "fieldReviews"
      ],
      "before": {
        "name": "Goodman Macquarie Park",
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "reported",
            "stage": "planned",
            "mw": null,
            "mwBasis": "unknown",
            "scopeId": "dcm-19094-unverified",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown",
            "sourceIds": [
              "dcm-19094"
            ],
            "note": "Directory reports Planned. No comparable IT capacity or commissioning date has been accepted from this listing."
          }
        ],
        "evidenceStatus": "directory-reported",
        "sourceIds": [
          "dcm-19094",
          "natural-earth-cities"
        ],
        "notes": [
          "Added from a public Data Center Map listing. Identity, technical specifications and location remain directory-reported until corroborated against operator or planning evidence."
        ],
        "aliases": null,
        "address": null,
        "fieldReviews": null
      },
      "after": {
        "name": "Goodman Project Apollo, Macquarie Park",
        "stages": [
          {
            "asOf": "2026-09-02",
            "mwQualifier": "maximum",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "goodman-apollo-approved-facility-power",
            "mw": 135,
            "mwBasis": "facility",
            "sourceIds": [
              "abc-goodman-apollo-consent-20260902"
            ],
            "note": "Approved maximum facility power consumption. Server IT allocation, construction commencement and commissioning dates are unverified.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "evidenceStatus": "profile-reviewed",
        "sourceIds": [
          "dcm-19094",
          "natural-earth-cities",
          "abc-goodman-apollo-consent-20260902"
        ],
        "notes": [
          "Added from a public Data Center Map listing. Identity, technical specifications and location remain directory-reported until corroborated against operator or planning evidence.",
          "Project Apollo was approved on 2 September 2026. The 135 MW consent is total facility power, with no separate IT allocation accepted."
        ],
        "aliases": [
          "Goodman Macquarie Park",
          "Project Apollo",
          "SSD-74069708"
        ],
        "address": {
          "street": "4–10 Talavera Road",
          "locality": "Macquarie Park",
          "region": "New South Wales",
          "postalCode": "",
          "country": "AU",
          "sourceIds": [
            "abc-goodman-apollo-consent-20260902"
          ],
          "verifiedOn": "2026-09-22"
        },
        "fieldReviews": [
          {
            "field": "identity",
            "outcome": "verified",
            "sourceIds": [
              "abc-goodman-apollo-consent-20260902"
            ],
            "note": "Named Project Apollo consent matches the 4–10 Talavera Road directory site.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "address",
            "outcome": "verified",
            "sourceIds": [
              "abc-goodman-apollo-consent-20260902"
            ],
            "note": "Consent identifies 4–10 Talavera Road. Precise coordinates remain unverified.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "capacity",
            "outcome": "verified",
            "sourceIds": [
              "abc-goodman-apollo-consent-20260902"
            ],
            "note": "135 MW is maximum total facility consumption, outside comparable IT subtotals.",
            "checkedOn": "2026-09-22"
          }
        ]
      }
    },
    {
      "id": "goodman-project-duke",
      "change": "added",
      "fields": [
        "id",
        "entityKind",
        "physicalSiteId",
        "name",
        "operator",
        "country",
        "region",
        "city",
        "lat",
        "lon",
        "locationPrecision",
        "address",
        "facilityType",
        "stages",
        "certification",
        "evidenceStatus",
        "sourceIds",
        "notes",
        "fieldReviews"
      ],
      "before": {
        "id": null,
        "entityKind": null,
        "physicalSiteId": null,
        "name": null,
        "operator": null,
        "country": null,
        "region": null,
        "city": null,
        "lat": null,
        "lon": null,
        "locationPrecision": null,
        "address": null,
        "facilityType": null,
        "stages": null,
        "certification": null,
        "evidenceStatus": null,
        "sourceIds": null,
        "notes": null,
        "fieldReviews": null
      },
      "after": {
        "id": "goodman-project-duke",
        "entityKind": "facility",
        "physicalSiteId": "goodman-project-duke",
        "name": "Goodman Project Duke, Mascot",
        "operator": "Operator not publicly identified",
        "country": "AU",
        "region": "New South Wales",
        "city": "Sydney",
        "lat": -33.871373,
        "lon": 151.212548,
        "locationPrecision": "city",
        "address": {
          "street": "2 and 10–22 Kent Road; 685 Gardeners Road",
          "locality": "Mascot",
          "region": "New South Wales",
          "postalCode": "",
          "country": "AU",
          "sourceIds": [
            "abc-duke-planning-20260922",
            "abc-duke-amendment-esd-20250521"
          ],
          "verifiedOn": "2026-09-22"
        },
        "facilityType": "unknown",
        "stages": [
          {
            "asOf": "2025-12-22",
            "mwQualifier": "reported",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "goodman-duke-approved-development",
            "mw": null,
            "mwBasis": "unknown",
            "sourceIds": [
              "abc-duke-planning-20260922",
              "abc-duke-amendment-esd-20250521"
            ],
            "note": "Project approved 22 December 2025. Portal summary says 90 MVA; the amended application specifies 120 MVA. ABC reports 120 MW. Final consent electrical boundary remains unresolved; no MVA-to-MW or IT conversion is made.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "certification": {
          "status": "unknown",
          "scope": null,
          "sourceIds": []
        },
        "evidenceStatus": "profile-reviewed",
        "sourceIds": [
          "abc-duke-planning-20260922",
          "abc-duke-amendment-esd-20250521",
          "natural-earth-cities"
        ],
        "notes": [
          "Goodman is the development proponent. The eventual operating tenant is unconfirmed.",
          "Application SSD-71368959 includes the Kent Road properties and, in the amendment, 685 Gardeners Road. Construction commencement is unverified."
        ],
        "fieldReviews": [
          {
            "field": "identity",
            "outcome": "verified",
            "sourceIds": [
              "abc-duke-planning-20260922",
              "abc-duke-amendment-esd-20250521"
            ],
            "note": "Named planning project and proponent are identified. The eventual operating tenant is unconfirmed.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "address",
            "outcome": "verified",
            "sourceIds": [
              "abc-duke-planning-20260922",
              "abc-duke-amendment-esd-20250521"
            ],
            "note": "Primary planning documents identify the street address. No exact map coordinates are inferred.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "capacity",
            "outcome": "conflicting",
            "sourceIds": [
              "abc-duke-planning-20260922",
              "abc-duke-amendment-esd-20250521"
            ],
            "note": "Published power measures differ between project documents and secondary reporting. No comparable IT contribution is accepted.",
            "checkedOn": "2026-09-22"
          }
        ]
      }
    },
    {
      "id": "nextdc-d2",
      "change": "updated",
      "fields": [
        "stages",
        "notes"
      ],
      "before": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1.5,
            "mwBasis": "IT",
            "scopeId": "nextdc-d2-construction",
            "includedInTotals": true,
            "expectedYear": 2026,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26",
              "nextdc-d2-page"
            ],
            "note": "Approximately 1.5 MW initial fit-out. Practical completion target 1HFY27 means July–December 2026; the target is not proof of commissioning."
          }
        ],
        "notes": [
          "The approximately 6 MW+ ultimate plan includes the initial phase and is not added again.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "Directory reconciliation: Directory parent campus includes D1 despite distinct published Harvey Street/Ryko Court addresses. Preserve accepted physicalSiteId pending operator campus-boundary reconciliation.",
          "City map markers are approximate. No exact facility coordinates have been verified."
        ]
      },
      "after": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1.5,
            "mwBasis": "IT",
            "scopeId": "nextdc-d2-construction",
            "includedInTotals": true,
            "expectedYear": 2026,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26",
              "nextdc-d2-page"
            ],
            "note": "Approximately 1.5 MW initial fit-out. Practical completion target 1HFY27 means July–December 2026; the target is not proof of commissioning."
          },
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "nextdc-d2-residual-planned-design",
            "mw": 4.5,
            "mwBasis": "IT",
            "sourceIds": [
              "nextdc-fy26"
            ],
            "note": "FY26 site appendix gives approximately 6 MW-plus total planned IT and approximately 1.5 MW initial capacity. The 4.5 MW residual is a disjoint remaining design after subtracting the included initial construction phase. The initial phase target does not date this remainder.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "notes": [
          "The approximately 6 MW+ ultimate plan includes the initial phase and is not added again.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "Directory reconciliation: Directory parent campus includes D1 despite distinct published Harvey Street/Ryko Court addresses. Preserve accepted physicalSiteId pending operator campus-boundary reconciliation.",
          "City map markers are approximate. No exact facility coordinates have been verified.",
          "Remaining design is separated from the initial construction phase: 6 minus 1.5 equals 4.5 MW. No completion date is assigned to the remainder."
        ]
      }
    },
    {
      "id": "nextdc-ge1",
      "change": "updated",
      "fields": [
        "stages",
        "notes"
      ],
      "before": {
        "stages": [
          {
            "asOf": "2026-06-30",
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1,
            "mwBasis": "IT",
            "scopeId": "nextdc-ge1-construction",
            "includedInTotals": true,
            "expectedYear": 2027,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26",
              "nextdc-ge1-page",
              "review-nextdc-fy26-announcement-20260827"
            ],
            "note": "Approximately 1 MW initial fit-out. Practical completion target 2HFY27 means January–June 2027; it is not evidence of opening."
          }
        ],
        "notes": [
          "Corio. Facility page lists 4.4 MW ultimate IT capacity; FY26 rounds the total plan to approximately 4 MW. Neither is represented as live capacity or added to the initial phase.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "City map markers are approximate. No exact facility coordinates have been verified."
        ]
      },
      "after": {
        "stages": [
          {
            "asOf": "2026-06-30",
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1,
            "mwBasis": "IT",
            "scopeId": "nextdc-ge1-construction",
            "includedInTotals": true,
            "expectedYear": 2027,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26",
              "nextdc-ge1-page",
              "review-nextdc-fy26-announcement-20260827"
            ],
            "note": "Approximately 1 MW initial fit-out. Practical completion target 2HFY27 means January–June 2027; it is not evidence of opening."
          },
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "nextdc-ge1-residual-planned-design",
            "mw": 3,
            "mwBasis": "IT",
            "sourceIds": [
              "nextdc-fy26"
            ],
            "note": "FY26 site appendix gives approximately 4 MW total planned IT and approximately 1 MW initial capacity. The 3 MW residual is a disjoint remaining design after subtracting the included initial construction phase. The initial phase target does not date this remainder.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "notes": [
          "Corio. Facility page lists 4.4 MW ultimate IT capacity; FY26 rounds the total plan to approximately 4 MW. Neither is represented as live capacity or added to the initial phase.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "City map markers are approximate. No exact facility coordinates have been verified.",
          "Remaining design is separated from the initial construction phase: 4 minus 1 equals 3 MW. No completion date is assigned to the remainder."
        ]
      }
    },
    {
      "id": "nextdc-sc2",
      "change": "updated",
      "fields": [
        "stages",
        "notes"
      ],
      "before": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1,
            "mwBasis": "IT",
            "scopeId": "nextdc-sc2-construction",
            "includedInTotals": true,
            "expectedYear": 2027,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26"
            ],
            "note": "Approximately 1 MW initial fit-out. Practical completion target 1HFY28 means July–December 2027; not a guaranteed operating date."
          }
        ],
        "notes": [
          "The 6 MW ultimate development plan includes this initial phase.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "City map markers are approximate. No exact facility coordinates have been verified."
        ]
      },
      "after": {
        "stages": [
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "construction",
            "mw": 1,
            "mwBasis": "IT",
            "scopeId": "nextdc-sc2-construction",
            "includedInTotals": true,
            "expectedYear": 2027,
            "dateConfidence": "target",
            "sourceIds": [
              "nextdc-fy26"
            ],
            "note": "Approximately 1 MW initial fit-out. Practical completion target 1HFY28 means July–December 2027; not a guaranteed operating date."
          },
          {
            "asOf": null,
            "mwQualifier": "approximate",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "nextdc-sc2-residual-planned-design",
            "mw": 5,
            "mwBasis": "IT",
            "sourceIds": [
              "nextdc-fy26"
            ],
            "note": "FY26 site appendix gives approximately 6 MW total planned IT and approximately 1 MW initial capacity. The 5 MW residual is a disjoint remaining design after subtracting the included initial construction phase. The initial phase target does not date this remainder.",
            "includedInTotals": true,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "notes": [
          "The 6 MW ultimate development plan includes this initial phase.",
          "Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.",
          "City map markers are approximate. No exact facility coordinates have been verified.",
          "Remaining design is separated from the initial construction phase: 6 minus 1 equals 5 MW. No completion date is assigned to the remainder."
        ]
      }
    },
    {
      "id": "stockland-khartoum-road",
      "change": "added",
      "fields": [
        "id",
        "entityKind",
        "physicalSiteId",
        "name",
        "operator",
        "country",
        "region",
        "city",
        "lat",
        "lon",
        "locationPrecision",
        "address",
        "facilityType",
        "stages",
        "certification",
        "evidenceStatus",
        "sourceIds",
        "notes",
        "fieldReviews"
      ],
      "before": {
        "id": null,
        "entityKind": null,
        "physicalSiteId": null,
        "name": null,
        "operator": null,
        "country": null,
        "region": null,
        "city": null,
        "lat": null,
        "lon": null,
        "locationPrecision": null,
        "address": null,
        "facilityType": null,
        "stages": null,
        "certification": null,
        "evidenceStatus": null,
        "sourceIds": null,
        "notes": null,
        "fieldReviews": null
      },
      "after": {
        "id": "stockland-khartoum-road",
        "entityKind": "facility",
        "physicalSiteId": "stockland-khartoum-road",
        "name": "Stockland 1–5 Khartoum Road Data Centre",
        "operator": "Operator not publicly identified",
        "country": "AU",
        "region": "New South Wales",
        "city": "Sydney",
        "lat": -33.871373,
        "lon": 151.212548,
        "locationPrecision": "city",
        "address": {
          "street": "1–5 Khartoum Road",
          "locality": "Macquarie Park",
          "region": "New South Wales",
          "postalCode": "",
          "country": "AU",
          "sourceIds": [
            "abc-khartoum-planning-20260922",
            "abc-khartoum-proponent-20250508"
          ],
          "verifiedOn": "2026-09-22"
        },
        "facilityType": "unknown",
        "stages": [
          {
            "asOf": "2026-03-11",
            "mwQualifier": "reported",
            "stage": "planned",
            "capacityRole": "design-envelope",
            "scopeId": "stockland-khartoum-ssd63235720-approved-development",
            "mw": null,
            "mwBasis": "unknown",
            "sourceIds": [
              "abc-khartoum-planning-20260922",
              "abc-khartoum-proponent-20250508"
            ],
            "note": "SSD-63235720 approved 11 March 2026. Portal summary says 35 MW, while ABC and an EPA submission describe 76.4 MW project power. Final consent boundary and IT allocation require reconciliation.",
            "includedInTotals": false,
            "expectedYear": null,
            "dateConfidence": "unknown"
          }
        ],
        "certification": {
          "status": "unknown",
          "scope": null,
          "sourceIds": []
        },
        "evidenceStatus": "profile-reviewed",
        "sourceIds": [
          "abc-khartoum-planning-20260922",
          "abc-khartoum-proponent-20250508",
          "natural-earth-cities"
        ],
        "notes": [
          "Stockland is the development proponent for SSD-63235720; the eventual operating tenant is unconfirmed.",
          "This is distinct from the AWS directory facility at 11–17 Khartoum Road. Nearby estate applications, including Road 1 SSD-80814238, are not added or merged without a building and parcel review."
        ],
        "fieldReviews": [
          {
            "field": "identity",
            "outcome": "verified",
            "sourceIds": [
              "abc-khartoum-planning-20260922",
              "abc-khartoum-proponent-20250508"
            ],
            "note": "Named planning project and proponent are identified. The eventual operating tenant is unconfirmed.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "address",
            "outcome": "verified",
            "sourceIds": [
              "abc-khartoum-planning-20260922",
              "abc-khartoum-proponent-20250508"
            ],
            "note": "Primary planning documents identify the street address. No exact map coordinates are inferred.",
            "checkedOn": "2026-09-22"
          },
          {
            "field": "capacity",
            "outcome": "conflicting",
            "sourceIds": [
              "abc-khartoum-planning-20260922",
              "abc-khartoum-proponent-20250508"
            ],
            "note": "Published power measures differ between project documents and secondary reporting. No comparable IT contribution is accepted.",
            "checkedOn": "2026-09-22"
          }
        ]
      }
    }
  ],
  "sources": [
    {
      "id": "abc-airtrunk-apollo-planning-20260922",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-airtrunk-apollo-planning-20260922",
        "title": "Apollo Place Data Centre SSD-67407231",
        "url": "https://www.planningportal.nsw.gov.au/major-projects/projects/apollo-place-data-centre",
        "publisher": "NSW Planning Portal",
        "locator": "Project description, determination date and decision",
        "summary": "45 MW data-centre development approved on 9 October 2025. No IT basis or construction commencement is established here.",
        "publishedAt": "2025-10-09",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-airtrunk-apollo-relationship-202505",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-airtrunk-apollo-relationship-202505",
        "title": "Apollo Place submissions report: relationship to existing SYD2",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=RFI-83215706%2120250507T071131.878+GMT",
        "publisher": "Urbis for AirTrunk, filed with NSW Planning",
        "locator": "Relationship with existing data centre at 1 Sirius Road; site description",
        "summary": "Development at 1 Apollo Place and 1 Sirius Road connects to the existing SYD2 data centre. It is an adjoining campus extension, not another independent campus.",
        "publishedAt": null,
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-duke-amendment-esd-20250521",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-duke-amendment-esd-20250521",
        "title": "Project Duke amendment ESD report",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=SSD-71368959%2120250704T003806.379+GMT",
        "publisher": "Arup for Goodman",
        "locator": "Project description; Site and Surrounding Context",
        "summary": "Amended development described as 120 MVA, at 2 and 10–22 Kent Road and 685 Gardeners Road. Final consent capacity boundary still requires reconciliation with the 90 MVA portal summary and ABC 120 MW.",
        "publishedAt": "2025-05-21",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-duke-planning-20260922",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-duke-planning-20260922",
        "title": "Project Duke SSD-71368959",
        "url": "https://www.planningportal.nsw.gov.au/major-projects/projects/project-duke-data-centre",
        "publisher": "NSW Planning Portal",
        "locator": "Project description and approval decision",
        "summary": "Approved 22 December 2025. Portal summary retains 90 MVA at 2 and 10–22 Kent Road; amendment papers specify 120 MVA and expanded land. Neither establishes 120 MW IT.",
        "publishedAt": "2025-12-22",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-echidna-address-20230705",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-echidna-address-20230705",
        "title": "Blacktown Council: Project Echidna address",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=PAE-59076708%2120230705T065140.809+GMT",
        "publisher": "Blacktown City Council",
        "locator": "Opening and submission heading",
        "summary": "Identifies SSD-47320208 at 10 Eastern Creek Drive, matching the existing Atlas AWS Eastern Creek directory record.",
        "publishedAt": "2023-07-05",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-echidna-planning-20260922",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-echidna-planning-20260922",
        "title": "Project Echidna SSD-47320208",
        "url": "https://www.planningportal.nsw.gov.au/major-projects/projects/project-echidna-data-centre-eastern-creek",
        "publisher": "NSW Planning Portal",
        "locator": "Project description and approval decision",
        "summary": "Project approved on 5 April 2024. Portal describes 35 MW operational capacity without identifying its electrical basis.",
        "publishedAt": "2024-04-05",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-goodman-apollo-consent-20260902",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-goodman-apollo-consent-20260902",
        "title": "Goodman Project Apollo signed consent",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=SSD-74069708%2120260903T232907.821+GMT",
        "publisher": "NSW Department of Planning, Housing and Infrastructure",
        "locator": "Signed consent; Schedule 1, site and development",
        "summary": "Approved 2 September 2026 at 4–10 Talavera Road, with 135 MW maximum power consumption. This is facility power, not IT load.",
        "publishedAt": "2026-09-02",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-khartoum-planning-20260922",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-khartoum-planning-20260922",
        "title": "1–5 Khartoum Road data centre SSD-63235720",
        "url": "https://www.planningportal.nsw.gov.au/major-projects/projects/1-5-khartoum-road-data-centre",
        "publisher": "NSW Planning Portal",
        "locator": "Project description, application number and decision",
        "summary": "Approved 11 March 2026. Portal summary states 35 MW; ABC and EPA refer to 76.4 MW total project power. IT boundary and final consent figure are not yet reconciled.",
        "publishedAt": "2026-03-11",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-khartoum-proponent-20250508",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-khartoum-proponent-20250508",
        "title": "Stockland Khartoum Road response to submissions",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=EXH-80609459%2120250509T062332.478+GMT",
        "publisher": "Urbis for Stockland",
        "locator": "Cover and section 1; SSD-63235720",
        "summary": "Identifies Stockland as proponent for the 1–5 Khartoum Road development. Separate nearby estate applications must not be combined without a parcel and building review.",
        "publishedAt": "2025-05-08",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-pipeline-table-v5-20260922",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-pipeline-table-v5-20260922",
        "title": "ABC development pipeline, all 27 table rows",
        "url": "https://datawrapper.dwcdn.net/044AN/5/",
        "publisher": "ABC News / Datawrapper",
        "locator": "Data centre development pipeline table, version 5: 27 entries across five pages.",
        "summary": "The 24 numeric MW rows total 3377.55 MW. The 90 MVA row and two unquantified rows are excluded from that arithmetic; campus, facility and IT scopes still differ.",
        "publishedAt": null,
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-poplars-cbr01-identity-20250120",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-poplars-cbr01-identity-20250120",
        "title": "DCI CBR01 Poplars ESD report",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=SSD-64287712%2120250222T000251.554+GMT",
        "publisher": "HDR for DCI Data Centers",
        "locator": "Cover; section 3; section 5.2 energy calculation",
        "summary": "Names the project CBR01, at 2 Wolseley Place Jerrabomberra, and explicitly separates 20 MW IT from 25.4 MW total demand.",
        "publishedAt": "2025-01-20",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "abc-poplars-final-assessment-20251106",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "locator",
        "summary",
        "publishedAt",
        "accessedAt"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "locator": null,
        "summary": null,
        "publishedAt": null,
        "accessedAt": null
      },
      "after": {
        "id": "abc-poplars-final-assessment-20251106",
        "title": "DCI Poplars final assessment SSD-64287712",
        "url": "https://majorprojects.planningportal.nsw.gov.au/prweb/PRRestService/mp/01/getContent?AttachRef=SSD-64287712%2120251109T224014.391+GMT",
        "publisher": "NSW Department of Planning, Housing and Infrastructure",
        "locator": "Table 2: construction phases; recommendation adopted 6 November 2025",
        "summary": "Approved project comprises 8 MW IT, 4 MW IT and 8 MW IT phases, totalling 20 MW IT within 25.4 MW total facility demand.",
        "publishedAt": "2025-11-06",
        "accessedAt": "2026-09-22"
      }
    },
    {
      "id": "market-abc-approved-pipeline-202609",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "accessedAt",
        "publishedAt",
        "locator",
        "summary"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "accessedAt": null,
        "publishedAt": null,
        "locator": null,
        "summary": null
      },
      "after": {
        "id": "market-abc-approved-pipeline-202609",
        "title": "The bigger, hungrier AI data centres set to escape looming water and power restrictions",
        "url": "https://www.abc.net.au/news/2026-09-11/the-ai-data-centres-set-to-escape-planned-restrictions/107097556",
        "publisher": "ABC News",
        "accessedAt": "2026-09-22",
        "publishedAt": "2026-09-11",
        "locator": "Bigger, hungrier section and embedded 27-project table; story updated 16 September 2026 (Australian time).",
        "summary": "ABC reports at least 3.38 GW across 27 approved or construction projects, using company capacity disclosures and planning-approved energy capacity. Its table mixes IT, facility, campus and other power definitions. The existing 1.5 GW figure is attributed to Data Centres Australia."
      }
    },
    {
      "id": "market-dca-dcbyte-forecast-202604",
      "change": "added",
      "fields": [
        "id",
        "title",
        "url",
        "publisher",
        "accessedAt",
        "publishedAt",
        "publishedDatePrecision",
        "locator",
        "summary"
      ],
      "before": {
        "id": null,
        "title": null,
        "url": null,
        "publisher": null,
        "accessedAt": null,
        "publishedAt": null,
        "publishedDatePrecision": null,
        "locator": null,
        "summary": null
      },
      "after": {
        "id": "market-dca-dcbyte-forecast-202604",
        "title": "Australian Data Centre Forecast Report, Issue 1 (April 2026)",
        "url": "https://datacentres.org.au/wp-content/uploads/2026/04/2026_Australian-Data-Centre-Forecast-Report-Issue-1-1.pdf",
        "publisher": "Data Centres Australia and DC Byte",
        "accessedAt": "2026-09-22",
        "publishedAt": "2026-04",
        "publishedDatePrecision": "month",
        "locator": "PDF pages 3–5: operational centre count, lifecycle definitions and national capacity table; effective 31 March 2026.",
        "summary": "National market estimates: about 1.5 GW operational IT capacity across 162 centres, with construction, committed and early-stage capacity reported separately. The 21.6 GW all-stage figure includes operating capacity. Operational capacity measures available fitted-out IT load, not utilisation."
      }
    }
  ],
  "research": [
    {
      "id": "market-au-approved-pipeline-abc-202609",
      "change": "added",
      "fields": [
        "category",
        "geography",
        "operator",
        "scope",
        "facilityIds",
        "status",
        "workloads",
        "hardware",
        "id",
        "title",
        "summary",
        "metrics",
        "asOf",
        "asOfPrecision",
        "sourceIds",
        "limitations"
      ],
      "before": {
        "category": null,
        "geography": null,
        "operator": null,
        "scope": null,
        "facilityIds": null,
        "status": null,
        "workloads": null,
        "hardware": null,
        "id": null,
        "title": null,
        "summary": null,
        "metrics": null,
        "asOf": null,
        "asOfPrecision": null,
        "sourceIds": null,
        "limitations": null
      },
      "after": {
        "category": "facility",
        "geography": "AU",
        "operator": null,
        "scope": "national",
        "facilityIds": [],
        "status": "reported",
        "workloads": [],
        "hardware": [],
        "id": "market-au-approved-pipeline-abc-202609",
        "title": "ABC: 27 approved or construction projects",
        "summary": "ABC News reports at least 3.38 GW across 27 approved or construction projects. Its September 2026 analysis draws on planning records and company documents, with checks by RenewMap and CBRE.",
        "metrics": [
          {
            "label": "Reported project capacity, rounded headline",
            "value": 3.38,
            "unit": "GW mixed power",
            "period": "September 2026",
            "qualifier": "minimum"
          },
          {
            "label": "Approved or construction projects",
            "value": 27,
            "unit": "projects",
            "period": "September 2026",
            "qualifier": "reported"
          }
        ],
        "asOf": "2026-09",
        "asOfPrecision": "month",
        "sourceIds": [
          "market-abc-approved-pipeline-202609",
          "abc-pipeline-table-v5-20260922"
        ],
        "limitations": "The reported 3.38 GW is rounded. The 24 numeric MW entries sum to 3,377.55 MW; the separate 90 MVA entry and two unquantified projects are excluded from that arithmetic. The entries mix computing-power, whole-facility and campus boundaries, so this is not a harmonised IT-power subtotal. The selected approved/construction projects do not cover every proposal in Australia, and approval does not guarantee delivery."
      }
    },
    {
      "id": "market-au-operating-dca-202603",
      "change": "added",
      "fields": [
        "category",
        "geography",
        "operator",
        "scope",
        "facilityIds",
        "status",
        "workloads",
        "hardware",
        "id",
        "title",
        "summary",
        "metrics",
        "asOf",
        "sourceIds",
        "limitations"
      ],
      "before": {
        "category": null,
        "geography": null,
        "operator": null,
        "scope": null,
        "facilityIds": null,
        "status": null,
        "workloads": null,
        "hardware": null,
        "id": null,
        "title": null,
        "summary": null,
        "metrics": null,
        "asOf": null,
        "sourceIds": null,
        "limitations": null
      },
      "after": {
        "category": "facility",
        "geography": "AU",
        "operator": null,
        "scope": "national",
        "facilityIds": [],
        "status": "reported",
        "workloads": [],
        "hardware": [],
        "id": "market-au-operating-dca-202603",
        "title": "Australia: about 1.5 GW of operational IT capacity",
        "summary": "Data Centres Australia and DC Byte estimate Australia had about 1.5 GW of operational IT capacity across 162 data centres at 31 March 2026. This provides a national market benchmark alongside the Atlas’s partial site-level evidence.",
        "metrics": [
          {
            "label": "National operational capacity",
            "value": 1500,
            "unit": "MW IT",
            "period": "31 March 2026",
            "qualifier": "approximate"
          },
          {
            "label": "Operational data centres in source inventory",
            "value": 162,
            "unit": "centres",
            "period": "31 March 2026",
            "qualifier": "reported"
          }
        ],
        "asOf": "2026-03-31",
        "sourceIds": [
          "market-dca-dcbyte-forecast-202604",
          "market-abc-approved-pipeline-202609"
        ],
        "limitations": "Operational capacity is the IT load supported by fitted-out halls available for use, not necessarily utilised capacity or live electricity demand. This rounded industry estimate has its own inventory and date. It is not an independently reconciled Atlas facility total and is never added to site subtotals or assigned to map pins."
      }
    },
    {
      "id": "market-au-pipeline-dca-202603",
      "change": "added",
      "fields": [
        "category",
        "geography",
        "operator",
        "scope",
        "facilityIds",
        "status",
        "workloads",
        "hardware",
        "id",
        "title",
        "summary",
        "metrics",
        "asOf",
        "sourceIds",
        "limitations"
      ],
      "before": {
        "category": null,
        "geography": null,
        "operator": null,
        "scope": null,
        "facilityIds": null,
        "status": null,
        "workloads": null,
        "hardware": null,
        "id": null,
        "title": null,
        "summary": null,
        "metrics": null,
        "asOf": null,
        "sourceIds": null,
        "limitations": null
      },
      "after": {
        "category": "facility",
        "geography": "AU",
        "operator": null,
        "scope": "national",
        "facilityIds": [],
        "status": "reported",
        "workloads": [],
        "hardware": [],
        "id": "market-au-pipeline-dca-202603",
        "title": "Australia’s capacity by development stage",
        "summary": "DC Byte’s national snapshot separates operating capacity, fit-out construction, committed development and early-stage proposals. At 31 March 2026 the combined total was about 21.6 GW, including existing operating capacity.",
        "metrics": [
          {
            "label": "Operational",
            "value": 1500,
            "unit": "MW IT",
            "period": "31 March 2026",
            "qualifier": "approximate"
          },
          {
            "label": "Under construction",
            "value": 200,
            "unit": "MW IT",
            "period": "31 March 2026",
            "qualifier": "approximate"
          },
          {
            "label": "Committed",
            "value": 3100,
            "unit": "MW IT",
            "period": "31 March 2026",
            "qualifier": "approximate"
          },
          {
            "label": "Early stage",
            "value": 16800,
            "unit": "MW IT",
            "period": "31 March 2026",
            "qualifier": "approximate"
          }
        ],
        "asOf": "2026-03-31",
        "sourceIds": [
          "market-dca-dcbyte-forecast-202604"
        ],
        "limitations": "Construction means data halls undergoing mechanical and electrical fit-out. Committed projects meet DC Byte’s confidence criteria through secured development inputs or an operator’s track record. Early-stage projects may never proceed. The source’s 21.6 GW total includes operating capacity; it is not all future supply. These March estimates and the Atlas’s later facility inventory have different coverage and stage rules and must not be added together."
      }
    }
  ]
}