DCI SYD02 Eastern Creek expansion: facility evidence profile

DCI Data Centers · Australia

DCI SYD02 Eastern Creek expansion

Report an error or share evidence ↗

Sydney, NSW · facility

Under constructionPlanned
Facility type
hyperscale
Location evidence
Approximate city location
Research status
Source-listed profile · 75% core-field coverage

Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.

Evidence by field

Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.

Address Source checked
The consolidated expansion consent identifies the shared site at 90 Peter Brock Drive, Eastern Creek. This does not establish an exact building coordinate.Checked 2026-09-22 · NSW Department of Planning, Housing and Infrastructure ↗
Capacity Source checked
Condition A5A(a) limits the expansion to 63 MW IT. This approved design maximum is separate from the existing SYD01 facility; construction-stage and commissioned IT capacity are undisclosed.Checked 2026-09-22 · NSW Department of Planning, Housing and Infrastructure ↗
Status Source checked
Early works have begun. Mod 2 was approved on 5 August 2026; approval is not commissioning.Checked 2026-09-22 · NSW Department of Planning, Housing and Infrastructure ↗ · DCI Data Centers ↗
Published street address

90 Peter Brock Drive, Eastern Creek, NSW

Checked 2026-09-22 · Map coordinates still to be verified

Open this address in maps ↗

Capacity & development

Under constructionNot disclosed

Power basis not established

Early demolition and tank-relocation works are under way. Mod 2 was approved on 5 August 2026; the new consent caps IT demand at 63 MW and lists 100 MVA electrical supply. No IT allocation to completed fit-out or the current early-works stage is established.

Planned≤ 63 MW

Power for servers, GPUs, storage & networking (IT power) · Source as of 2026-08-05

Approved maximum IT demand of the new expansion development under condition A5A(a), separate from the existing SYD01 facility. Counted once as a design envelope. Early works have begun, but no phase-specific IT MW is allocated to construction; 100 MVA supply and 93.6 MW backup generation are not added.

Proposed or approved design capacity. Included in the planning inventory, not a dated delivery forecast or a claim of committed supply.

Government certification

Certification not verified

No verified certification scope has been assigned to this record. Unknown does not mean uncertified.

What certification covers →

Scope and context

  • Map location, when supplied, represents the city rather than a verified facility coordinate.
  • Shares the existing SYD01 physical site. The locations page uses SYD02/SYD03; held as one development record until that relationship is resolved.
  • Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.
  • Directory reconciliation: The public publisher withholds exact location. This match uses named identity only and does not use hidden embedded coordinates or addresses.
  • The Mod 2 consent supersedes the July 2026 article saying the 63 MW modification is still sought. Certification of the SYD01 enclave does not extend to this development.

Compute, workloads & commercial commitments

Site-specific workloads, GPU inventory and customer contracts are not established by the cited evidence. Electrical capacity and AI-ready specifications alone do not establish these details.

Explore demand, compute types and commitments →

Evidence trail

  1. DCI SYD02 construction update ↗

    DCI Data Centers · checked 2026-09-10

    July 2026 article; opening paragraphs and construction staging

  2. DCI data centre locations ↗

    DCI Data Centers · checked 2026-09-10

    Our Centers and Sites In Development

  3. DCI Sydney 02: directory profile and specifications ↗

    Data Center Map · checked 2026-09-11

    Public listing 11354; overview, specs tabs. Address/location header and labelled technical specification rows.

  4. Natural Earth populated places, 1:10m ↗

    Natural Earth · checked 2026-09-10

    Australia and New Zealand populated-place features

  5. Eastern Creek data centre expansion, consolidated consent including Mod 2 ↗

    NSW Department of Planning, Housing and Infrastructure · checked 2026-09-22 · published 2026-08-05

    Schedule 1 site and modification table; condition A5A(a): IT demand cap