AUSTRALIA · UNDER CONSTRUCTION

602.3 MW

Disclosed computing-power capacity being built, supported by construction or fit-out evidence.

See contributing sites →

AUSTRALIA · PLANNED IT DESIGN

8,661.1 MW

Proposed and approved computing-power designs, including labelled upper limits. Development potential, subject to approvals, investment and delivery.

See contributing sites →

What is included?

The figures cover documented IT power: electricity available to servers, GPUs, storage and networking, excluding building overheads. Campus totals and their component phases count once. Planned capacity includes design limits; it does not establish committed supply or a delivery date.

55 of 267 grouped Australian sites have a comparable IT figure across operating, construction or planned stages. These are disclosed subtotals, with coverage gaps, rather than complete national totals.

Comparing published pipeline estimates.

Market-wide estimates, approved-project inventories and city maps differ in coverage, stage and date. Their source figures provide context; grid, facility and computing-power figures are not interchangeable. The national source counts only halls undergoing mechanical and electrical fit-out as construction; the site inventory also includes earlier building works.

The published national development picture

A market-wide view groups capacity by its delivery stage. The source date and stage definitions are retained below; its figures are separate from the documented-site subtotals above.

Market capacityAustraliaReported observation

Australia’s capacity by development stage

DC Byte’s national snapshot separates operating capacity, fit-out construction, committed development and early-stage proposals. At 31 March 2026 the combined total was about 21.6 GW, including existing operating capacity.

Operational
≈ 1,500 MW IT
31 March 2026
Under construction
≈ 200 MW IT
31 March 2026
Committed
≈ 3,100 MW IT
31 March 2026
Early stage
≈ 16,800 MW IT
31 March 2026
Evidence scope
National
Evidence as-of date
2026-03-31

How to read this: Construction means data halls undergoing mechanical and electrical fit-out. Committed projects meet DC Byte’s confidence criteria through secured development inputs or an operator’s track record. Early-stage projects may never proceed. The source’s 21.6 GW total includes operating capacity; it is not all future supply. These March estimates and the Atlas’s later facility inventory have different coverage and stage rules and must not be added together.

Inspect the source
Link to this evidence ↗

Proposed IT designs in planning records

These designs are included once in the planned IT figure above. Each is an upper project limit, subject to its own assessment and delivery decisions.

Facility specificationAustraliaAnnouncement

Bundey: 600 MW proposed IT design within an 800 MW electricity project

The federal referral specifies three proposed data halls of up to 200 MW IT each at Bundey, South Australia.

Proposed IT design ceiling
≤ 600 MW IT
Referral dated 31 July 2026
Electricity project ceiling
≤ 800 MW grid/project power
Campus proposal
Evidence scope
Named facility · IREN
Evidence as-of date
2026-07-31

How to read this: The IT and grid figures are different boundaries and are not additive. The IT figure is an upper design limit in a referral; the reviewed records do not establish state development consent, construction or operating capacity. No site-specific GPU deployment or tenant contract is established by the referral.

Inspect 2 sources
  • Bundey Data Centre Campus, EPBC referral 2026/10605 ↗

    Australian Government EPBC Act Public Portal · checked 2026-09-23

    Project description, Key Project Elements: three halls each up to 200 MW IT; referral project number 2026/10605 and status. Attachment 00-2026-10605 Referral.pdf, sections 1.2 and 2.2, dated 31 July 2026, identifies Lot 69 Bundey Church Road.

  • Bundey Data Centre Campus referral attachment ↗

    TAS 1 Holdings / Australian Government EPBC Act Public Portal · checked 2026-09-23 · published 2026-07-31

    Referral PDF, sections 1.2 and 2.2: applicant ownership by IREN; Lot 69 Bundey Church Road; three proposed halls, each up to 200 MW IT.

Link to this evidence ↗
Facility specificationAustraliaAnnouncement

Julius Avenue: revised 76 MW proposed IT load

A later lodged design for 6–8 Julius Avenue specifies 76 MW IT across eight halls, down from an earlier 115.2 MW IT concept.

Proposed IT design ceiling
≤ 76 MW IT
Revision 06 dated 9 December 2025
Evidence scope
Named facility · ISPT
Evidence as-of date
2025-12-09

How to read this: The old 115.2 MW IT design and 169–170 MW whole-site figures are not additions. The current revision says 120 MW maximum whole-site power. The application remains under assessment; design is not installed capacity or a delivery forecast.

Inspect 3 sources
Link to this evidence ↗
Facility specificationAustraliaAnnouncement

Project Mars: 60 MW maximum proposed IT load

The applicant's ESD report for 12 Mars Road gives a maximum 60 MW IT load, within 81 MW maximum whole-site electricity demand.

Proposed IT design ceiling
≤ 60 MW IT
Applicant report dated 17 February 2026
Evidence scope
Named facility · Goodman
Evidence as-of date
2026-02-17

How to read this: The project is at Response to Submissions, not approved or built. The 81 MW full-site figure and portal's approximately 90 MW description are not separate IT increments.

Inspect 2 sources
Link to this evidence ↗

A published view of approved projects

Published project inventories can differ in their planning stage, coverage and electrical definition. This estimate is presented separately from the site subtotals above.

Market capacityAustraliaReported observation

ABC: 27 approved or construction projects

ABC News reports at least 3.38 GW across 27 approved or construction projects. Its September 2026 analysis draws on planning records and company documents, with checks by RenewMap and CBRE.

Reported project capacity, rounded headline
≥ 3.38 GW mixed power
September 2026
Approved or construction projects
27 projects
September 2026
Evidence scope
National
Evidence as-of date
2026-09

How to read this: The reported 3.38 GW is rounded. The 24 numeric MW entries sum to 3,377.55 MW; the separate 90 MVA entry and two unquantified projects are excluded from that arithmetic. The entries mix computing-power, whole-facility and campus boundaries, so this is not a harmonised IT-power subtotal. The selected approved/construction projects do not cover every proposal in Australia, and approval does not guarantee delivery.

Inspect 2 sources
Link to this evidence ↗

City-level source maps

Certified Strategic’s Sydney and Melbourne maps contain March and April 2026 observations with mixed electrical definitions. Each source label is retained below.

Secondary map labels, reproduced for reconciliation only
MapRowsOperating labelConstruction labelPlanned labelConstruction + planned
Sydney ↗581,281 MW1,449.5 MW3,943 MW5,392.5 MW
Melbourne ↗521,112 MW899 MW1,347 MW2,246 MW

Sydney’s map rows total 5,392.5 MW of construction plus planned labels, against its approximately 5.2 GW headline. Melbourne’s equivalent is 2,246 MW, against its approximately 4.7 GW headline. These headline estimates and facility rows represent different inventories and should not be combined.

74 of 110 source observations have a primary-source comparison below. Evidence status identifies supported details, conflicting figures and unresolved claims.

Project evidence and source comparisons.

Compare Certified Strategic’s March and April 2026 map figures with operator and planning documents. Each entry identifies the supported details, unresolved questions and relevant facility profiles.

110 of 110 map observations

SYDNEY · 2026-04

AirTrunk/ISPT Mamre Rd

AirTrunk / ISPT · Kemps Creek

1,000 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

July 2026 amendment reduces the same Mamre campus from the former 1.04 GW IT design to approximately 750 MW IT. Public engineering appendix identifies AirTrunk SYD 4. Proposal remains in assessment; construction and 2030/2037 scenario dates are not verified delivery. Do not add older six-building directory capacities or the potential KNBDC alias.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

Keppel Morwell

Keppel · Morwell

720 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Keppel states up to 720 MW gross power in phases over time. The map labels it IT load. Planning approvals and power/water contracting are pre-development tasks; no commissioned power or signed customer contract was established.

Inspect supporting evidence (1)

SYDNEY · 2026-04

NEXTDC S7 (OpenAI)

NEXTDC · Eastern Creek

612 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Map interactive 612 MW is the planning operational-capacity headline, while operator FY 26 reports approximately 550 MW-plus IT. Visible map table separately says 600 MW; none are additive.

Inspect supporting evidence (2)

SYDNEY · 2026-04

CDC Marsden Park

CDC Data Centres · Marsden Park

504 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

Marsden Park 1 is operational; additional buildings are under construction for FY28-29 delivery. Capacity is contained in the NSW portfolio total and is not separately allocated.

Inspect supporting evidence (3)

SYDNEY · 2026-04

STACK SYD01

STACK Infrastructure · Erskine Park

450 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Operator states 360 MW campus and 450+ MW gross substation capacity. 450 is explicitly gross and cannot enter IT totals.360 basis still needs confirmation.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

AirTrunk MEL2

AirTrunk · Tullamarine

354 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

354+ MW campus scale is primary-supported; source does not explicitly define IT basis or allocate current construction phases. Keep as announced campus envelope, not 354 MW commissioned or fully verified construction.

Inspect supporting evidence (1)

SYDNEY · 2026-04

NEXTDC S4

NEXTDC · Horsley Park

350 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

Dated FY 26 report supersedes old 350 MW design: 250 MW in progress plus 115 MW in plan equals 365 MW IT. Builder mid-2027 target is not applied to the remaining 115 MW.

Inspect supporting evidence (2)

SYDNEY · 2026-04

AirTrunk SYD3

AirTrunk · Huntingwood

330 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Operator/builder describe more than 400 MW ultimate campus, with expansion underway July 2026 to mid-2028. Neither 330 MW all-operating nor 400 MW incremental addition is established.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

STACK MEL02

STACK Infrastructure · Truganina

252 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

Operator subtitle advertises 250 MW critical capacity, body 252 MW and 300+ MW gross substation. The page has no dated construction allocation. Resolve internal capacity discrepancy and lifecycle before accepting 252 MW IT construction.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

NEXTDC M3

NEXTDC · West Footscray

225 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

FY26 built capacity at an operational facility: designed IT power of fitted-out halls, not measured electricity demand, utilisation or immediately available supply.

Inspect supporting evidence (4)

MELBOURNE · 2026-03

CDC Brooklyn BK3

CDC Data Centres · Brooklyn

195 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

Approximately 130 MW of operating primary ICT capacity, derived from CDC’s Victorian regional total. Brooklyn is CDC’s only operating Victorian campus; the government confirms two operational facilities, while the September investor update places Laverton’s first opening in late FY27. The regional figure is rounded to the nearest 10 MW and is assigned once to the campus, without duplicating BK1 and BK2.

Inspect supporting evidence (4)

MELBOURNE · 2026-03

AirTrunk MEL1

AirTrunk · Derrimut

185 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Initial 5 MW IT opening tranche. Later completed expansions are separate. Completed May 2023 expansion added 20+ MW IT. This is a separate increment from the 2017 opening tranche. Other campus phases are not yet separately quantified as completed IT load. The 25 MW subtotal is a documented lower bound, not the campus total.

Inspect supporting evidence (12)

SYDNEY · 2026-04

ISPT Julius Avenue

ISPT · North Ryde

170 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

The map's 170 MW was an older whole-site power concept, not IT load. A later lodged revision states 76 MW IT and 120 MW maximum site power across eight halls. The application remains More Information Required.

Inspect supporting evidence (3)

MELBOURNE · 2026-03

NEXTDC M4

NEXTDC · Port Melbourne

162 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

FY26 records approximately 150 MW total IT, with 10 MW in progress; the same boundary leaves 140 MW planned. The map 162 MW is not the current like-for-like IT target.

Inspect supporting evidence (1)
  • NEXTDC FY26 Results Presentation ↗

    PDF pp 4–6 (contracted, billing and forward order book), p 18 (built/in-progress table and definitions; visually checked), pp 30–32 (named development rows)

SYDNEY · 2026-04

AirTrunk SYD2

AirTrunk · Lane Cove West

158 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Only the third-phase 30 MW increment is evidenced here. AirTrunk confirms completion; contemporaneous DCD reporting explicitly identifies the same expansion as IT capacity. Neither source establishes that the whole 120+ MW campus was fitted out. Approximately 50 MW for the first two opened phases, derived from the operator 120+ MW campus total less its 70 MW final-two-phase expansion. Both earlier phases were already open in June 2023. Contemporaneous reporting identifies the campus electrical basis as IT load. This rounded derivation is separate from the completed 30 MW phase 3 increment; phase 4 is not assumed operational.

Inspect supporting evidence (14)

MELBOURNE · 2026-03

CDC Brooklyn BK1/BK2

CDC Data Centres · Brooklyn

155 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Approximately 130 MW of operating primary ICT capacity, derived from CDC’s Victorian regional total. Brooklyn is CDC’s only operating Victorian campus; the government confirms two operational facilities, while the September investor update places Laverton’s first opening in late FY27. The regional figure is rounded to the nearest 10 MW and is assigned once to the campus, without duplicating BK1 and BK2.

Inspect supporting evidence (4)

MELBOURNE · 2026-03

CDC Laverton

CDC Data Centres · Laverton North

150 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

150 MW construction announcement is dated 17 February 2025, but latest campus scale is 400+ MW. Definitions and current phase allocations are not identified as IT. Latest deck targets first buildinglateFY27 and nexttwoFY28; overlapping 150 and 400 cannot both count.

Inspect supporting evidence (3)

SYDNEY · 2026-04

Project Blue Tongue

TBC · Wetherill Park

132 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Project Blue Tongue is SSD-59416728 at 3 Davis Road, Lot 1 DP864615, approved 20 December 2024. The updated ESD specifies maximum 132.43 MW IT (66 + 66 + 0.43), retained in the final assessment scheme with 160.85 MW total consumption. It is distinct from 2 Davis Road. The operator is unnamed and no current installed/construction MW is established.

Inspect supporting evidence (3)

SYDNEY · 2026-04

Goodman Project Pluto

Goodman Group · Guildford West

126 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

July 2026 approved design states 68 MW IT and 100 MW total. Map 126 MW is superseded.

Inspect supporting evidence (2)

SYDNEY · 2026-04

CDC EC1-EC4

CDC Data Centres · Eastern Creek

123 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

The investor presentation confirms EC5 and EC6 delivery in addition to the existing EC1-4. EC5 and EC6 are recorded as operating; no separate building MW allocation is disclosed.

Inspect supporting evidence (3)

SYDNEY · 2026-04

AirTrunk SYD1

AirTrunk · Huntingwood

121 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Conservative 121 MW IT lower bound for the completed SYD1 campus. The final building was completed in July 2022 at a reported 130 MW IT campus scale. The later platform announcement states 121+ MW, while the current campus page retains 130+ MW. Their difference is not explained. No hosted tenant or final phase is added separately.

Inspect supporting evidence (9)

MELBOURNE · 2026-03

NEXTDC M2

NEXTDC · Tullamarine

120 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

FY26 built capacity at an operational facility: designed IT power of fitted-out halls, not measured electricity demand, utilisation or immediately available supply.

Inspect supporting evidence (4)

SYDNEY · 2026-04

GreenSquareDC SYD1

GreenSquareDC · Norwest

110 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

Operator current capacity card explicitly labels a 100 MW-plus IT campus and 15 MW first-stage refurbishment. This does not support an exact 110 MW active construction increment. Full campus envelope remains non-additive until retained, refurbished and future IT scopes reconcile.

Inspect supporting evidence (2)

SYDNEY · 2026-04

CDC EC5/EC6

CDC Data Centres · Eastern Creek

108 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

The investor presentation confirms EC5 and EC6 delivery in addition to the existing EC1-4. EC5 and EC6 are recorded as operating; no separate building MW allocation is disclosed.

Inspect supporting evidence (3)

MELBOURNE · 2026-03

STACK MEL01C/D

STACK Infrastructure · Truganina

108 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

MEL01A is a 36 MW critical-capacity building delivered in 2023. The contractor reports staged hall fit-out continuing alongside live operations in June 2025. The fully fitted IT subtotal is not disclosed, so the 36 MW design rating remains outside the operating subtotal.

Inspect supporting evidence (9)

SYDNEY · 2026-04

KNBDC Mamre Road

KNBDC · Kemps Creek

100 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

Government names KNBDC Pty Ltd Mamre Road Data Centre Campus. Its separately plotted 100 MW observation has not been shown to represent capacity additional to the same Mamre proposal, now amended to approximately 750 MW IT. Treat as a potential duplicate.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Stockland/EdgeConneX MPark

Stockland / EdgeConneX · Macquarie Park

100 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Map 100 MW conflicts with planning headline 35 MW and older comments 76.4 MW. Stockland portfolio 450 MW secured cannot be allocated to this campus by inference.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Microsoft Kemps Creek

Microsoft · Kemps Creek

96 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

May 2026 operator update says Building One handed to operations and Building Two construction ongoing. 96 MW cannot all be attributed to construction without the phase split.

Inspect supporting evidence (1)

SYDNEY · 2026-04

NEXTDC S3/S6

NEXTDC · Artarmon

93.5 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

FY26 built capacity at an operational facility: designed IT power of fitted-out halls, not measured electricity demand, utilisation or immediately available supply. The 68 MW built and 12 MW in-progress split comes from the FY26 results; the facility page supports the 80 MW overall specification only. FY26 built capacity at an operational facility: designed IT power of fitted-out halls, not measured electricity demand, utilisation or immediately available supply.

Inspect supporting evidence (5)

SYDNEY · 2026-04

Goodman Project Duke

Goodman Group · Mascot

90 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

90 MVA is the current planning headline. Older ESD seeks 120 MVA; consent scope needs detailed reconciliation. Neither is 90 MW IT.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Goodman Project Mars

Goodman Group · Lane Cove West

90 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

The map's 90 MW is whole-site power and does not establish IT load. The applicant's February 2026 report specifies 60 MW maximum IT load inside 81 MW maximum site load; the project remains at Response to Submissions.

Inspect supporting evidence (2)

SYDNEY · 2026-04

NEXTDC S5

NEXTDC · North Ryde

80 MW as labelled

Planned in the source map

Source map ↗

Claim corroborated

FY 26 discloses approximately 80 MW-plus IT design, in planning subject to DA. This is a design-envelope target, not commissioned supply.

Inspect supporting evidence (1)
  • NEXTDC FY26 Results Presentation ↗

    PDF pp 4–6 (contracted, billing and forward order book), p 18 (built/in-progress table and definitions; visually checked), pp 30–32 (named development rows)

MELBOURNE · 2026-03

PGIM Truganina

PGIM Real Estate · Truganina

80 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

PermitPA2504032 approves1 Oroya Drive data centre on6 May 2026. Full 29-page officer assessment has no MW disclosure, so map 80 MW remains secondary-reported and IT basis unverified.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Stockland Kemps Creek

Stockland · Kemps Creek

80 MW as labelled

Planned in the source map

Source map ↗

Not independently established

Stockland namesKemps Creek in 450 MW aggregate secured power across 3 sites; no 80 MW primary allocation.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Stockland Wetherill Park

Stockland · Wetherill Park

80 MW as labelled

Planned in the source map

Source map ↗

Not independently established

Stockland namesWetherill Park in 450 MW aggregate secured power across 3 sites; no 80 MW primary allocation.

Inspect supporting evidence (1)

SYDNEY · 2026-04

AWS Eastern Creek

AWS · Eastern Creek

70 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Directory-only AWS identity and 70 MW claim need operator/planning corroboration. Exact physical/phase scope remains unverified.

SYDNEY · 2026-04

Digital Realty Macquarie Park

Digital Realty · Macquarie Park

70 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

Issuer reports 30 MW operating white-space IT capacity across its Sydney portfolio at 30 June 2026. It does not allocate that figure to the named buildings. The portfolio control is counted once.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Digital Realty SYD12

Digital Realty · North Ryde

70 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

Issuer reports 30 MW operating white-space IT capacity across its Sydney portfolio at 30 June 2026. It does not allocate that figure to the named buildings. The portfolio control is counted once.

Inspect supporting evidence (2)

SYDNEY · 2026-04

DCI SYD02

DCI Data Centres · Eastern Creek

64 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

Actual Mod 2 consolidated consent approved 5 August 2026 caps the expansion at 63 MW IT and 100 MVA. Early works are underway; allocated construction-stage IT MW is not disclosed. Accepted 63 MW design is not the older 64 MW secondary construction claim.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

Vantage MEL1

Vantage Data Centers · Tullamarine

64 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Operator data sheet explicitly states one planned data centre and 64 MW critical IT. The map operational classification is unsupported; accept 64 MW planned IT with no opening year.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Starwood/Doma/Telstra

Starwood/Doma/Telstra · Minchinbury

62 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

62 MW IT and 90 MVA are primary-confirmed approved design. Construction was scheduled early 2026 but actual commencement is not confirmed by the November 2025 release; retain planned.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Goodman SYD01

Goodman Group · Artarmon

61 MW as labelled

Construction in the source map

Source map ↗

Claim corroborated

Operator explicitly says 61 MW IT under construction, 90 MW utility power, five 12.2 MW phases. Only first phase targets 2028.

Inspect supporting evidence (1)

SYDNEY · 2026-04

AWS Gregory Hills

AWS · Gregory Hills

53 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Final November 2025 assessment confirms 53 MW IT within 61.7 MW total, approved 21 November. June 2026 modification changes substation layout. This is 43–61 Turner Road, distinct from the 146/148 Turner campus. The primary record identifies Arup acting for an unnamed multinational; AWS attribution remains unverified. Accept only the approved design envelope, without a construction/completion inference.

Inspect supporting evidence (3)

SYDNEY · 2026-04

Microsoft Honeman Close

Microsoft · Blacktown

50 MW as labelled

Planned in the source map

Source map ↗

Different primary evidence

Planning portal describes 96 MW, not map 50 MW. IT basis, operator identity and currently approved scope not established.

Inspect supporting evidence (1)

SYDNEY · 2026-04

DigiCo Expansion

DigiCo · Ultimo

47.5 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

Same campus as Global Switch operating row. Remaining expansion is 52 MW from 36 installed to 88 ultimate; old 47.5 MW does not reconcile.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Macquarie IC3 Super West

Macquarie Data Centres · Macquarie Park

47 MW as labelled

Construction in the source map

Source map ↗

Different primary evidence

47 MW IT design comprises 6 MW initial fit-out, 13 MW next phase (June 2027 target) and 28 MW remaining design; not 47 MW commissioned or all completing September 2026.

Inspect supporting evidence (2)

SYDNEY · 2026-04

DigiCo (Global Switch)

DigiCo · Ultimo

42.5 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Current operator reports 36 MW installed IT; dated issuer announcement confirms 88 MW whole-site goal and remaining 52 MW expansion. Legacy Global Switch name is the same campus.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

STACK MEL01A

STACK Infrastructure · Truganina

36 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

MEL01A is a 36 MW critical-capacity building delivered in 2023. The contractor reports staged hall fit-out continuing alongside live operations in June 2025. The fully fitted IT subtotal is not disclosed, so the 36 MW design rating remains outside the operating subtotal.

Inspect supporting evidence (10)

MELBOURNE · 2026-03

STACK MEL01B

STACK Infrastructure · Truganina

36 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

MEL01A is a 36 MW critical-capacity building delivered in 2023. The contractor reports staged hall fit-out continuing alongside live operations in June 2025. The fully fitted IT subtotal is not disclosed, so the 36 MW design rating remains outside the operating subtotal.

Inspect supporting evidence (10)

MELBOURNE · 2026-03

Microsoft MEL04

Microsoft · Yarraville

35 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Microsoft public community updates corroborate named development/activity, but do not disclose the map 35 MW IT per building. Lifecycle notices are scoped to specific buildings and dates.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Microsoft MEL05

Microsoft · Yarraville

35 MW as labelled

Construction in the source map

Source map ↗

Partly corroborated

Microsoft public community updates corroborate named development/activity, but do not disclose the map 35 MW IT per building. Lifecycle notices are scoped to specific buildings and dates.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Microsoft MEL07

Microsoft · Tullamarine

35 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Microsoft public community updates corroborate named development/activity, but do not disclose the map 35 MW IT per building. Lifecycle notices are scoped to specific buildings and dates.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Microsoft Woods Road

Microsoft · Truganina

35 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Microsoft public community updates corroborate named development/activity, but do not disclose the map 35 MW IT per building. Lifecycle notices are scoped to specific buildings and dates.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

AWS Cobblebank

AWS · Cobblebank

30 MW as labelled

Planned in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

AWS Mickleham AI Superhub

AWS · Mickleham

30 MW as labelled

Planned in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

AWS Truganina

AWS · Truganina

30 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Centuria Yarraville Dev

Centuria Capital · Yarraville

30 MW as labelled

Planned in the source map

Source map ↗

Partly corroborated

Centuria investor presentation lists Yarraville as property development/power optionality. It does not disclose 30 MW secured or planned IT at this site.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Keppel Gore Hill

Keppel DC · Artarmon

30 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Gore Hill identity requires owner/operator/building reconciliation. 30 MW current IT is not corroborated in the collected primary evidence.

MELBOURNE · 2026-03

NEXTDC Craigieburn

NEXTDC · Craigieburn

30 MW as labelled

Planned in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

SYDNEY · 2026-04

NEXTDC S2

NEXTDC · Macquarie Park

30 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

NEXTDC reported the final S2 data halls fitted out at 30 June 2021, bringing built capacity to 30 MW. Its current facility page continues to advertise 30 MW IT capacity. This is a historical installed-capacity observation, not a newly inferred commissioning date.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Digital Realty SYD10/SYD11

Digital Realty · Erskine Park

25 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Issuer reports 30 MW operating white-space IT capacity across its Sydney portfolio at 30 June 2026. It does not allocate that figure to the named buildings. The portfolio control is counted once.

Inspect supporting evidence (2)

SYDNEY · 2026-04

Equinix SY3

Equinix · Alexandria

25 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Named facility is corroborated. The 25 MW installed IT assertion has not been verified by a site-specific primary power disclosure.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Telstra InfraCo St Leonards

Telstra InfraCo · St Leonards

20 MW as labelled

Operating in the source map

Source map ↗

Not independently established

No current site-specific primary basis for 20 MW located in the reviewed Telstra material; no capacity imported.

SYDNEY · 2026-04

AWS Smeaton Grange

AWS · Smeaton Grange

18 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map locality may cover several AWS buildings. Its 18 MW assertion lacks a reconciled primary capacity boundary.

SYDNEY · 2026-04

Macquarie DC IC2/IC3

Macquarie Data Centres · Macquarie Park

18 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Macquarie commissioned environmental assessment states IC2 was operating at full capacity, unlike partially operating IC3 East. The operator identifies IC2 capacity as6 MW IT. This is allocated within the21 MW installed Australian portfolio, not added on top of it.

Inspect supporting evidence (5)

MELBOURNE · 2026-03

NEXTDC M1

NEXTDC · Port Melbourne

16 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Historical fitted-out IT capacity derived from NEXTDC FY20: Victoria built25 MW less M2 installed10 MW equals15 MW at M1. M3 had not been built. The current M1 page advertises16 MW IT design capacity; the extra1 MW is not treated as installed without a dated fit-out disclosure. This allocation is part of the Australian NEXTDC portfolio total.

Inspect supporting evidence (3)
  • M1 Melbourne ↗

    Named facility main description and IT design specification

  • NEXTDC FY26 Results Presentation ↗

    PDF pp 4–6 (contracted, billing and forward order book), p 18 (built/in-progress table and definitions; visually checked), pp 30–32 (named development rows)

  • NEXTDC FY20 Full-Year Results ↗

    Facilities capacity table, at 30 June 2020; S2 installed22 MW; M2 technical specifications installed10 MW; fitted-out capacity definition

SYDNEY · 2026-04

NEXTDC S1

NEXTDC · Macquarie Park

16 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Historical fitted-out IT capacity derived from NEXTDC FY20: NSW built38 MW less S2 installed22 MW equals16 MW at S1. S3 was under development, with no built allocation. The current S1 operator specification remains16 MW IT. This allocation is part of the Australian NEXTDC portfolio total.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

Equinix ME4

Equinix · Derrimut

15 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Equinix primary facility specifications establish identity and services. This review did not establish the map MW as commissioned IT; cabinet density and electrical supply ratings cannot substitute.

Inspect supporting evidence (2)
  • Melbourne ME4 ↗

    Named facility heading; opening service description; Building/Facilities specification tables; Available products. Original address and site marker separately retained in saved public inline configuration.

  • Equinix colocation operational coverage ↗

    APAC > Australia table; explicit 24/7 or non-24/7 on-site operational coverage

MELBOURNE · 2026-03

Equinix ME2

Equinix · Port Melbourne

12 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Equinix primary facility specifications establish identity and services. This review did not establish the map MW as commissioned IT; cabinet density and electrical supply ratings cannot substitute.

Inspect supporting evidence (2)
  • Melbourne ME2 ↗

    Named facility heading; opening service description; Building/Facilities specification tables; Available products. Original address and site marker separately retained in saved public inline configuration.

  • Equinix colocation operational coverage ↗

    APAC > Australia table; explicit 24/7 or non-24/7 on-site operational coverage

MELBOURNE · 2026-03

Fujitsu Noble Park

Fujitsu · Noble Park

12 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Fujitsu fact sheet specifies site capacity to 12 MVA and dual8 MVA feeds. MVA cannot be relabelled 12 MW IT without a power-factor and boundary conversion.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Digital Realty MEL10

Digital Realty · Deer Park

11.5 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Issuer reports 9.6 MW operating white-space IT capacity in Melbourne at 31 December 2025, distinct from the map’s individual building ratings. The regional total is retained once; no unsupported building split is inferred.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Centuria Clayton DC

Centuria Industrial REIT · Clayton

10 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Centuria identifies this as the existing Telstra Data Complex. It overlaps the Telstra Clayton row. No evidence of a separate 10 MW operating campus was found.

Inspect supporting evidence (2)

MELBOURNE · 2026-03

Digital Realty MEL12

Digital Realty · Deer Park

10 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Issuer reports 9.6 MW operating white-space IT capacity in Melbourne at 31 December 2025, distinct from the map’s individual building ratings. The regional total is retained once; no unsupported building split is inferred.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Equinix SY6

Equinix · Silverwater

10 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Identity is corroborated but 10 MW installed IT is not independently established.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Telstra Clayton

Telstra InfraCo · Clayton

10 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Primary brochure target power is 20 MW from 10+10 MW dual redundant feeds. Neither 20 nor 10 is a demonstrated commissioned IT total. Also overlaps Centuria landlord row.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Digital Realty MEL11

Digital Realty · Deer Park

9 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Issuer reports 9.6 MW operating white-space IT capacity in Melbourne at 31 December 2025, distinct from the map’s individual building ratings. The regional total is retained once; no unsupported building split is inferred.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Vocus SYD04

Vocus Communications · Rosebery

9 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Vocus network directory does not corroborate the map 9 MW installed IT at a unique SYD 04 boundary.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

NTT Port Melbourne

NTT · Port Melbourne

6.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Equinix ME5

Equinix · West Melbourne

6 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Equinix primary facility specifications establish identity and services. This review did not establish the map MW as commissioned IT; cabinet density and electrical supply ratings cannot substitute.

Inspect supporting evidence (2)
  • Melbourne ME5 ↗

    Named facility heading; opening service description; Building/Facilities specification tables; Available products. Original address and site marker separately retained in saved public inline configuration.

  • Equinix colocation operational coverage ↗

    APAC > Australia table; explicit 24/7 or non-24/7 on-site operational coverage

SYDNEY · 2026-04

Rackspace SYD2

Rackspace Technology · Erskine Park

6 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Operator specifies 5.6 MW UPS power and 10 MVA utility power. Neither is a verified 6 MW installed IT figure; tenant/building overlap also requires review.

Inspect supporting evidence (1)

SYDNEY · 2026-04

DigiCo SYD2

DigiCo Infrastructure REIT · Artarmon

5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Directory identity is present, but 5 MW current installed IT has not been primary-verified.

MELBOURNE · 2026-03

Equinix ME1

Equinix · Port Melbourne

5 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Equinix primary facility specifications establish identity and services. This review did not establish the map MW as commissioned IT; cabinet density and electrical supply ratings cannot substitute.

Inspect supporting evidence (2)
  • Melbourne ME1 ↗

    Named facility heading; opening service description; Building/Facilities specification tables; Available products. Original address and site marker separately retained in saved public inline configuration.

  • Equinix colocation operational coverage ↗

    APAC > Australia table; explicit 24/7 or non-24/7 on-site operational coverage

SYDNEY · 2026-04

Macquarie DC IC1

Macquarie Data Centres · Sydney CBD

5 MW as labelled

Operating in the source map

Source map ↗

Different primary evidence

Map 5 MW differs from operator profile 2 MW IT design. Neither is independently evidenced as a new installed-capacity observation here.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

NTT Melbourne 1

NTT · Altona North

5 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

NTT brochure identifies Melbourne1 and up-to 12 kW/rack; it does not establish total5 MW IT. Do not multiply unspecified rack counts or use electrical redundancy as capacity.

Inspect supporting evidence (1)

SYDNEY · 2026-04

Unisys Rhodes

Unisys · Rhodes

5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Public Unisys site search did not yield a current Rhodes-specific 5 MW primary disclosure.

MELBOURNE · 2026-03

Datacom @ AirTrunk MEL1

Datacom · Derrimut

4 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Datacom listing is a service/tenant presence at AirTrunkMEL1 and shares physicalSiteIdairtrunk-mel1. Its4 MW cannot be added to the parent campus. Exact electrical allocation remains unverified.

MELBOURNE · 2026-03

Interactive Melbourne

Interactive · Port Melbourne

4 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

DXC Technology Melbourne

DXC Technology · Burwood East

3.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Vocus Mitcham

Vocus · Mitcham

2.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Vocus Port Melbourne

Vocus · Port Melbourne

2.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

5G Networks Melbourne

5G Networks · Melbourne CBD

2 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Epsilon DC

Epsilon DC · Port Melbourne

2 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

SYDNEY · 2026-04

5G Networks NSDC

5G Networks · St Leonards

1.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

No primary 1.5 MW installed IT disclosure tied to this precise facility found in the bounded operator search.

SYDNEY · 2026-04

5G Networks SDC

5G Networks · Pyrmont

1.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

No primary 1.5 MW installed IT disclosure tied to this precise facility found in the bounded operator search.

MELBOURNE · 2026-03

Micron21

Micron21 · Kilsyth South

1.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

ResetData AI-F1

ResetData · Docklands

1.5 MW as labelled

Operating in the source map

Source map ↗

Partly corroborated

Centuria May 2026 briefing identifies1.1 MW compute and staged GPU deployment, not the map1.5 MW installed IT. Power allocation, GPU utilisation and facility capacity are distinct.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

Vocus Collins Street

Vocus · Melbourne CBD

1.5 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

MELBOURNE · 2026-03

Biztactix Sunshine

Biztactix · Sunshine

1 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

SYDNEY · 2026-04

Datacom St Leonards

Datacom · St Leonards

1 MW as labelled

Operating in the source map

Source map ↗

Not independently established

Datacom service presence is not proof of an additional standalone 1 MW physical data centre. Tenant/campus boundary unresolved.

Inspect supporting evidence (1)

MELBOURNE · 2026-03

OMNIconnect

OMNIconnect · Carrum Downs

1 MW as labelled

Operating in the source map

Source map ↗

Not independently established

The map-specific MW and lifecycle allocation have not been corroborated by a primary disclosure in this review. Existing directory or identity evidence is not verification of capacity.

The wider development picture.

These project envelopes, electricity connections, portfolio disclosures and contracts add context. They use different boundaries and units, and overlap named sites. Read each separately; they are not an extra subtotal to add to the cards above.

Commercial commitmentAustraliaContracted

Western Downs developer confirms an Anthropic lease

The developer confirms Anthropic has signed a long-term lease at Western Downs Digital Park. The proposed campus remains subject to planning and regulatory approvals.

Evidence scope
Named facility · Zerra DC
Evidence as-of date
Applicable date not stated
Workloads described
Not specified in this evidence

How to read this: Current primary material does not quantify leased IT MW, identify building-one capacity or confirm a 2027 delivery date. Reported campus capacity and an unquantified lease are different claims.

Inspect the source
  • Home | WDDP ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Lease commitment; How much electricity will the project use; Will the campus be built all at once

Link to this evidence ↗
Facility specificationAustraliaAnnouncement

Western Downs discloses apparent electrical power per stage

Western Downs Digital Park describes four development stages and approximately 540 MVA of total facility demand per stage. That is an electrical design specification, not measured consumption or disclosed IT capacity.

Total facility demand design per stage
≈ 540 MVA
Undated developer FAQ reviewed 22 September 2026
Planned development stages
≤ 4 stages
Undated developer FAQ reviewed 22 September 2026
Evidence scope
Named facility · Zerra DC
Evidence as-of date
Applicable date not stated

How to read this: Do not convert 540 MVA into IT MW, add it to a reported 360 MW figure, or combine the four-building application with a separate six-building engineering scenario.

Inspect the source
  • Home | WDDP ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Lease commitment; How much electricity will the project use; Will the campus be built all at once

Link to this evidence ↗
Facility specificationAustraliaAnnouncement

Aurora has a staged pathway toward gigawatt-scale development

1414 Degrees disclosed a Heads of Agreement for up to 1 GW of data-centre infrastructure, beginning with an indicative 17 MW campus and an approximately 200 MW anchor campus as connection infrastructure progresses.

Ultimate data-centre pathway, power basis unspecified
≤ 1,000 MW
Heads of Agreement announced 27 July 2026
Nested starter campus, power basis unspecified
≈ 17 MW
Heads of Agreement announced 27 July 2026
Nested anchor campus, power basis unspecified
≈ 200 MW
Heads of Agreement announced 27 July 2026
Evidence scope
Named facility
Evidence as-of date
2026-07-27

How to read this: The figures are nested and cannot be added. No explicit IT basis, named operating partner, final customer contract or absolute completion date is disclosed. Energy assets are separate. The Heads of Agreement is non-binding except specified exclusivity/right-of-first-refusal provisions.

Inspect 4 sources
Link to this evidence ↗
Facility specificationANZAnnouncement

CDC reports a 3.9 GW leasable ANZ pipeline

September 2026 investor update reports 3.9 GW leasable pipeline as at 30 June 2026. Earlier 1.7 GW leasable capacity corresponded to a 2.5 GW built capacity pipeline. The definitions differ and cannot be summed.

Total leasable pipeline
3,900 MW leasable
2026-06-30
Evidence scope
Operator portfolio · CDC
Evidence as-of date
2026-06-30

How to read this: Includes existing operating and future capacity across Australia and New Zealand. It is not additional pipeline or site-allocated IT capacity and is not additive to facility totals.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

Keppel Morwell AI Data Centre Campus: disclosed development boundary

Already recorded in Atlas. The ultimate campus ceiling is not additive to component phases.

Gross facility power
≤ 720 MW gross power
ultimate-campus; planned
Evidence scope
Named facility · Keppel Data Centres
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Already recorded in Atlas. The ultimate campus ceiling is not additive to component phases.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

AirTrunk MEL2 Melbourne: disclosed development boundary

Primary campus announcement. The map construction classification has not been independently established.

Disclosed campus specification
≥ 354 MW unspecified electrical boundary
ultimate-campus; planned
Evidence scope
Named facility · AirTrunk
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Primary campus announcement. The map construction classification has not been independently established.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

AirTrunk MEL1 Melbourne: disclosed development boundary

Do not label all 276 MW operating or all of it future capacity.

Disclosed campus specification
≥ 276 MW unspecified electrical boundary
ultimate-campus-including-operating; unknown
Evidence scope
Named facility · AirTrunk
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Do not label all 276 MW operating or all of it future capacity.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

CDC Brooklyn Campus: disclosed development boundary

Includes built BK1/BK2 and future capacity. The whole 350 MW must not be added to its component buildings.

Disclosed campus specification
≥ 350 MW unspecified electrical boundary
ultimate-campus-including-operating; unknown
Evidence scope
Named facility · CDC
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Includes built BK1/BK2 and future capacity. The whole 350 MW must not be added to its component buildings.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

CDC Laverton Campus: disclosed development boundary

Operator says the campus is under construction. Phase completion targets differ. Do not add the older 150 MW announcement again.

Disclosed campus specification
≥ 400 MW unspecified electrical boundary
ultimate-campus; construction
Evidence scope
Named facility · CDC
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Operator says the campus is under construction. Phase completion targets differ. Do not add the older 150 MW announcement again.

Inspect 2 sources
Link to this evidence ↗
Facility specificationAustraliaReported observation

STACK MEL01 campus: disclosed development boundary

Four building design values are 36, 36, 54 and 54 MW. This envelope includes the completed first facility.

Disclosed campus specification
180 MW unspecified electrical boundary
ultimate-campus-including-operating; unknown
Evidence scope
Named facility · STACK Infrastructure
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Four building design values are 36, 36, 54 and 54 MW. This envelope includes the completed first facility.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

STACK MEL02 campus: disclosed development boundary

Hold numeric IT promotion until the 250/252 MW discrepancy and lifecycle allocation are resolved.

Disclosed campus specification
252 MW campus capacity; conflicting250MWcriticalheading
ultimate-campus; unknown
Evidence scope
Named facility · STACK Infrastructure
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Hold numeric IT promotion until the 250/252 MW discrepancy and lifecycle allocation are resolved.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

Centuria Clayton proposed data centre: disclosed development boundary

Separate development from the existing Telstra facility. A ceiling does not represent committed capacity.

Disclosed campus specification
≤ 40 MW unspecified electrical boundary
separate-expansion; planned
Evidence scope
Named facility · Centuria Industrial REIT
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Separate development from the existing Telstra facility. A ceiling does not represent committed capacity.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

Project Atlas Data Centre Eastern Creek: disclosed development boundary

Grid connection apparent-power envelope, not IT MW.

Apparent electrical power
500 MVA
Project design; planned
Evidence scope
Named facility · Goodman
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Grid connection apparent-power envelope, not IT MW.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

CDC Marsden Park Campus: disclosed development boundary

Approved power-consumption envelope across six buildings; current fit-out MW not disclosed.

Disclosed campus specification
504 MW (facility-power)
Project design; construction
Evidence scope
Named facility · CDC
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Approved power-consumption envelope across six buildings; current fit-out MW not disclosed.

Inspect 2 sources
Link to this evidence ↗
Facility specificationAustraliaReported observation

STACK SYD01 campus: disclosed development boundary

Operator gross substation capacity; 360 MW separate campus headline has no explicit IT basis on this page.

Gross facility power
≥ 450 MW (gross-power)
Project design; planned
Evidence scope
Named facility · STACK Infrastructure
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Operator gross substation capacity; 360 MW separate campus headline has no explicit IT basis on this page.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

AirTrunk SYD3 Sydney West: disclosed development boundary

Whole campus envelope; incremental extension not quantified. No 400 MW addition assumed.

Disclosed campus specification
≥ 400 MW (unspecified-design-power)
Project design; construction
Evidence scope
Named facility · AirTrunk
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Whole campus envelope; incremental extension not quantified. No 400 MW addition assumed.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

GreenSquareDC SYD1: disclosed development boundary

Current operator capacity card explicitly labels 100 MW-plus IT for the whole campus, including a 15 MW first-stage refurbishment of an existing centre.

Disclosed campus specification
≥ 100 MW IT design
Whole-campus design; construction under way
Evidence scope
Named facility · GreenSquareDC
Evidence as-of date
Applicable date not stated

How to read this: Whole-campus design is not an additive construction increment. The existing/refurbished/remaining delivery split needs reconciliation; passing the first-stage Q3 2026 target does not establish commissioning.

Inspect 2 sources
Link to this evidence ↗
Facility specificationAustraliaReported observation

Goodman Macquarie Park: disclosed development boundary

Approved Apollo total power consumption across eight halls at 4–10 Talavera Road. It is not an explicit IT-load observation.

Disclosed campus specification
135 MW (facility-power)
Project design; planned
Evidence scope
Named facility · Goodman
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Approved Apollo total power consumption across eight halls at 4–10 Talavera Road. It is not an explicit IT-load observation.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

IREN Bundey campus: disclosed development boundary

An 800 MW electricity connection supports a proposed 600 MW IT campus design across three halls. Energisation from 2028 is a connection target, not delivery of the whole campus.

Electricity connection capacity
≤ 800 MW (grid-connection)
Whole campus connection; proposed envelope
Evidence scope
Named facility · IREN
Evidence as-of date
Applicable date not stated

How to read this: The 800 MW connection and 600 MW proposed IT design have distinct electrical boundaries and are not additive. A federal referral decision is recorded; state development consent and operating halls are not established by the reviewed records. No completion year for the full design is established.

Inspect 2 sources
Link to this evidence ↗
Facility specificationAustraliaReported observation

Firmus Bell Bay AI Factory: disclosed development boundary

Not an IT figure. Site approval claim from secondary reporting still needs current council verification.

Electricity connection capacity
≈ 288 MW (grid-demand)
Whole Bell Bay/George Town site; proposed envelope
Evidence scope
Named facility · Firmus
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Not an IT figure. Site approval claim from secondary reporting still needs current council verification.

Inspect the source
Link to this evidence ↗
Facility specificationAustraliaReported observation

CDC Maddington Campus: disclosed development boundary

CDC reports more than 200 MW for the eventual campus without an explicit IT-versus-facility power basis. The first of four buildings is under construction and targeting January 2027; its MW allocation is undisclosed.

Disclosed campus specification
≥ 200 MW (unspecified)
Whole planned Perth campus; proposed envelope
Evidence scope
Named facility · CDC
Evidence as-of date
Applicable date not stated

How to read this: Whole-campus design capacity overlaps the first building under construction and is excluded from the comparable IT subtotal. January 2027 is the first-building target only, not a complete-campus date. The secondary 150 MW IT claim lacks a verified primary locator.

Inspect 3 sources
Link to this evidence ↗
Facility specificationAustraliaReported observation

Beetaloo Digital Campus: disclosed development boundary

Original ASX PDF page 7 visually checked: 2 GW is explicitly on-site gas-fired power generation. No IT conversion or addition is justified.

Disclosed campus specification
≤ 2,000 MW (generation)
Energy generation supporting the planned Weddell campuses; proposed envelope
Evidence scope
Named facility · Beetaloo Energy
Evidence as-of date
Applicable date not stated

How to read this: This observation has its own electrical and physical boundary. It is not an additional contribution to the comparable IT subtotal, a GPU count or a delivery forecast. Original ASX PDF page 7 visually checked: 2 GW is explicitly on-site gas-fired power generation. No IT conversion or addition is justified.

Inspect the source
  • beetaloo-launch-pdf ↗

    Beetaloo Energy / Northern Territory Government · checked 2026-09-22 · published 2026-07-22

    Original ASX announcement bundle PDF page 7, reproduced NT Government media release

Link to this evidence ↗

Interpreting the evidence.

A planning approval establishes an approved proposal, not completed construction. A published address establishes location, not installed capacity. Use the document date and the stated electrical boundary when comparing figures.

Cloud regions, hosted services and landlord records may refer to the same physical facilities. The downloadable evidence preserves source observations and their references; a directory match alone does not establish separate capacity or government certification.

Read the counting rules → · Send a correction or primary evidence →