Western Downs Digital Park: facility evidence profile

Zerra DC · Australia

Western Downs Digital Park

Report an error or share evidence ↗

Kogan, Queensland · campus

Planned
Facility type
colocation
Location evidence
Approximate city location
Research status
Profile reviewed · 50% core-field coverage

Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.

Evidence by field

Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.

Identity Source checked
Developer identifies Western Downs Digital Park, consortium led by Zerra DC with ADC and Macquarie Capital.Checked 2026-09-22 · Western Downs Digital Park / Zerra DC ↗
Status Source checked
Proposed campus under assessment and approvals; no construction commencement stated.Checked 2026-09-22 · Western Downs Digital Park / Zerra DC ↗
Capacity Not found in checked sources
Primary apparent-power specification does not establish 360 MW IT per building.Checked 2026-09-22 · Western Downs Digital Park / Zerra DC ↗
Contracts Source checked
Developer confirms signed Anthropic lease; capacity and delivery date not quantified on primary page.Checked 2026-09-22 · Western Downs Digital Park / Zerra DC ↗

Capacity & development

PlannedNot disclosed

Power basis not established

Four-stage proposed development remains subject to planning and regulatory approval. Current primary power specification is approximately 540 MVA total facility demand per stage, not an IT MW allocation.

Government certification

Certification not verified

No verified certification scope has been assigned to this record. Unknown does not mean uncertified.

What certification covers →

Scope and context

  • Added from a public Data Center Map listing. Identity and location remain directory-reported until corroborated against operator or planning evidence.
  • Primary identity corroborated on 22 September 2026. Preserve the existing campus and its directory children as one physical site. Developer reports four planned buildings and approximately 540 MVA total facility demand per stage.
  • Anthropic lease is confirmed by the developer. The lease does not establish that the entire campus is leased, permitted, constructed or operating.

Compute, workloads & commercial commitments

Commercial commitmentAustraliaContracted

Western Downs developer confirms an Anthropic lease

The developer confirms Anthropic has signed a long-term lease at Western Downs Digital Park. The proposed campus remains subject to planning and regulatory approvals.

Evidence scope
Named facility · Zerra DC
Evidence as-of date
Applicable date not stated
Workloads described
Not specified in this evidence

How to read this: Current primary material does not quantify leased IT MW, identify building-one capacity or confirm a 2027 delivery date. Reported campus capacity and an unquantified lease are different claims.

Inspect the source
  • Home | WDDP ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Lease commitment; How much electricity will the project use; Will the campus be built all at once

Link to this evidence ↗
Facility specificationAustraliaAnnouncement

Western Downs discloses apparent electrical power per stage

Western Downs Digital Park describes four development stages and approximately 540 MVA of total facility demand per stage. That is an electrical design specification, not measured consumption or disclosed IT capacity.

Total facility demand design per stage
≈ 540 MVA
Undated developer FAQ reviewed 22 September 2026
Planned development stages
≤ 4 stages
Undated developer FAQ reviewed 22 September 2026
Evidence scope
Named facility · Zerra DC
Evidence as-of date
Applicable date not stated

How to read this: Do not convert 540 MVA into IT MW, add it to a reported 360 MW figure, or combine the four-building application with a separate six-building engineering scenario.

Inspect the source
  • Home | WDDP ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Lease commitment; How much electricity will the project use; Will the campus be built all at once

Link to this evidence ↗
Explore demand, compute types and commitments →

Evidence trail

  1. Western Downs Digital Park: directory profile and specifications ↗

    Data Center Map · checked 2026-09-11

    Public listing 18946; overview, specs tabs. Address/location header and labelled technical specification rows.

  2. Home | WDDP ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Lease commitment; How much electricity will the project use; Will the campus be built all at once

  3. zerra-western-downs-newsletter ↗

    Western Downs Digital Park / Zerra DC · checked 2026-09-22

    Water facts: Annual water use at a glance; No water cooling

  4. OpenStreetMap place features for towns outside the Natural Earth set ↗

    OpenStreetMap contributors · checked 2026-11-03

    Nominatim settlement results for Moss Vale, Morwell, Warragul, Arrowsmith, Kogan, Stratford (Taranaki) and Flying Fish Cove (Christmas Island), checked 3 November 2026.