Goodman · Australia
Goodman Project Mars
Report an error or share evidence ↗
Sydney, NSW · facility
- Facility type
- colocation
- Location evidence
- Approximate city location
- Research status
- Profile reviewed · 75% core-field coverage
Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.
Evidence by field
Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.
- Identity Source checked
- Applicant's final-lodgement report identifies Project Mars at 12 Mars Road, Lane Cove West.Checked 2026-09-23 · HDR for Project Mars applicant, lodged with NSW Planning ↗
- Address Source checked
- The planning report identifies 12 Mars Road; a street-level map point has not been independently verified.Checked 2026-09-23 · HDR for Project Mars applicant, lodged with NSW Planning ↗
- Capacity Source checked
- 60 MW maximum IT load is explicitly distinct from 81 MW maximum total site load and portal's approximately 90 MW description.Checked 2026-09-23 · HDR for Project Mars applicant, lodged with NSW Planning ↗
- Status Source checked
- NSW Planning lists Response to Submissions; no approval or construction start is verified.Checked 2026-09-23 · NSW Planning Portal ↗
12 Mars Road, Lane Cove West, NSW, 2066
Checked 2026-09-23 · Map coordinates still to be verified
Open this address in maps ↗Capacity & development
Power for servers, GPUs, storage & networking (IT power) · Source as of 2026-02-17
Applicant ESD report defines 60 MW maximum site IT load and 81 MW maximum whole-site load. This application remains at Response to Submissions; the 60 MW is an unapproved IT design ceiling, not construction or operating capacity.
Proposed or approved design capacity. Included in the planning inventory, not a dated delivery forecast or a claim of committed supply.
Government certification
Certification not verified
No verified certification scope has been assigned to this record. Unknown does not mean uncertified.
What certification covers →Scope and context
- Added from a public Data Center Map listing. Identity and location remain directory-reported until corroborated against operator or planning evidence.
- 60 MW is the proposed site IT design limit. Total facility electricity demand and an earlier portal headline are not additional IT capacity.
Compute, workloads & commercial commitments
Project Mars: 60 MW maximum proposed IT load
The applicant's ESD report for 12 Mars Road gives a maximum 60 MW IT load, within 81 MW maximum whole-site electricity demand.
- Proposed IT design ceiling
- ≤ 60 MW IT Applicant report dated 17 February 2026
- Evidence scope
- Named facility · Goodman
- Evidence as-of date
- 2026-02-17
How to read this: The project is at Response to Submissions, not approved or built. The 81 MW full-site figure and portal's approximately 90 MW description are not separate IT increments.
Inspect 2 sources
- Project Mars data centre ESD report, Issue B ↗
HDR for Project Mars applicant, lodged with NSW Planning · checked 2026-09-23 · published 2026-02-17
Energy-use calculation: 60 MW Maximum Site IT Load, PUE 1.35, 81 MW Maximum Total Site Load; site at 12 Mars Road, Lane Cove West.
- Project Mars Data Centre - NSW Planning Portal ↗
NSW Planning Portal · checked 2026-09-22
Project description and current status
Evidence trail
- Goodman Project Mars: directory profile and specifications ↗
Data Center Map · checked 2026-09-11
Public listing 14686; location, overview, specs tabs. Address/location header and labelled technical specification rows.
- Project Mars data centre ESD report, Issue B ↗
HDR for Project Mars applicant, lodged with NSW Planning · checked 2026-09-23 · published 2026-02-17
Energy-use calculation: 60 MW Maximum Site IT Load, PUE 1.35, 81 MW Maximum Total Site Load; site at 12 Mars Road, Lane Cove West.
- Project Mars Data Centre - NSW Planning Portal ↗
NSW Planning Portal · checked 2026-09-22
Project description and current status
- Natural Earth populated places, 1:10m ↗
Natural Earth · checked 2026-09-10
Australia and New Zealand populated-place features