Goodman · Australia
Goodman SYD01 Artarmon
Report an error or share evidence ↗
Sydney, New South Wales · facility
- Facility type
- hyperscale
- Location evidence
- Approximate city location
- Research status
- Profile reviewed · 63% core-field coverage
Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.
Evidence by field
Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.
- Capacity Source checked
- Construction figure is total project IT design under construction, not all capacity commissioned or all scheduled for 2028. First phase is 12.2 MW; do not add the 90 MW utility envelope.Checked 2026-09-22 · Goodman ↗
2 Lanceley Place, Artarmon, New South Wales, 2064
Checked 2026-09-11 · Map coordinates still to be verified
Open this address in maps ↗Capacity & development
Power for servers, GPUs, storage & networking (IT power)
Goodman explicitly describes the 61 MW IT project as under construction, delivered in five 12.2 MW phases. Only the first phase has a 2028 target; no date is attributed to the whole 61 MW.
Government certification
Certification not verified
No verified certification scope has been assigned to this record. Unknown does not mean uncertified.
What certification covers →Scope and context
- Exact street address is source-backed; no exact map coordinates have been verified.
- Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.
- Directory reconciliation: Directory address range is 2–8 Lanceley Place; accepted source is 2 Lanceley Place. Same SYD01 identity; full range is not independently verified.
- Construction figure is total project IT design under construction, not all capacity commissioned or all scheduled for 2028. First phase is 12.2 MW; do not add the 90 MW utility envelope.
Compute, workloads & commercial commitments
Site-specific workloads, GPU inventory and customer contracts are not established by the cited evidence. Electrical capacity and AI-ready specifications alone do not establish these details.
Explore demand, compute types and commitments →Evidence trail
- Goodman begins SYD01 construction ↗
Goodman · checked 2026-09-11 · published 2026-03-02
2 March 2026 announcement; project and phased-delivery paragraphs
- Goodman Australian data centre overview ↗
Goodman · checked 2026-09-11
Global data centre power bank > Goodman SYD01
- Goodman SYD01: directory profile and specifications ↗
Data Center Map · checked 2026-09-11
Public listing 16908; location, overview, specs tabs. Address/location header and labelled technical specification rows.
- Goodman SYD01 | Sydney data centre ↗
Goodman · checked 2026-09-22
Key figures; project overview; IT specifications FAQ
- Natural Earth populated places, 1:10m ↗
Natural Earth · checked 2026-09-10
Australia and New Zealand populated-place features