- Facility type
- colocation
- Location evidence
- Corroborated site location
- Research status
- Profile reviewed · 63% core-field coverage
Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.
Evidence by field
Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.
- Address Source checked
- The social impact assessment lodged with SSD-70889211 is titled '105 and 113 Hollinsworth Road, Marsden Park'; CDC's project page names Hollinsworth Road. The two lots form one campus and no cited source allocates buildings to lots.Checked 2026-11-03 · NSW Planning Portal (Major Projects) ↗ · NSW Planning Portal ↗
- Coordinates Source checked
- Address node for 105 Hollinsworth Road, Marsden Park matches the campus address. One campus point is used for every building. Numbered address or named building matched through OpenStreetMap; not a surveyed boundary or guaranteed entrance. Data © OpenStreetMap contributors (ODbL 1.0).Checked 2026-11-03 · NSW Planning Portal (Major Projects) ↗ · NSW Planning Portal ↗ · OpenStreetMap contributors ↗
- Status Source checked
- Approved under SSD-70889211 on 27 November 2025 as one of six data centre buildings; Infratil reports campus-level construction for FY28-29 deliveries but no cited source states that this building is under construction. Planned, with no capacity accepted.Checked 2026-11-03 · NSW Planning Portal ↗ · Infratil Limited ↗
105 and 113 Hollinsworth Road, Marsden Park, NSW, 2765
Checked 2026-11-03 · Site coordinates verified
Address node for 105 Hollinsworth Road, Marsden Park matches the campus address. One campus point is used for every building. Numbered address or named building matched through OpenStreetMap; not a surveyed boundary or guaranteed entrance. Data © OpenStreetMap contributors (ODbL 1.0).
Open this address in maps ↗Capacity & development
Power basis not established
Directory reports Planned. No comparable IT capacity or commissioning date has been accepted from this listing.
Government certification
Certification not verified
No verified certification scope has been assigned to this record. Unknown does not mean uncertified.
What certification covers →Scope and context
- The directory links this entry to CDC Marsden Park Campus. It shares a grouped site boundary with its reported parent; a hosted provider or child building is not counted as another independent site.
- First listed from a public Data Center Map listing; identity, address and lifecycle have since been checked against the operator, planning and news sources cited on this record.
Compute, workloads & commercial commitments
Site-specific workloads, GPU inventory and customer contracts are not established by the cited evidence. Electrical capacity and AI-ready specifications alone do not establish these details.
Related operator-wide evidence
These disclosures describe the operator’s portfolio. They are not assigned to this facility or included in its power totals.
CDC reports a 3.9 GW leasable ANZ pipeline
September 2026 investor update reports 3.9 GW leasable pipeline as at 30 June 2026. Earlier 1.7 GW leasable capacity corresponded to a 2.5 GW built capacity pipeline. The definitions differ and cannot be summed.
- Total leasable pipeline
- 3,900 MW leasable 2026-06-30
- Evidence scope
- Operator portfolio · CDC
- Evidence as-of date
- 2026-06-30
How to read this: Includes existing operating and future capacity across Australia and New Zealand. It is not additional pipeline or site-allocated IT capacity and is not additive to facility totals.
Inspect the source
- CDC Infratil investor update, 16 September 2026 ↗
CDC / Infratil · checked 2026-09-22 · published 2026-09-16
Slides: CDC Group snapshot; Then and now; Operating capacity has more than doubled; Construction is progressing; footnotes defining pipeline
CDC Australian operating ICT capacity: approximately 470 MW
CDC reports operating primary ICT capacity of approximately 120 MW in the ACT, 220 MW in NSW and 130 MW in Victoria at 30 June 2026. The regional figures are rounded to the nearest 10 MW.
- Operating primary ICT capacity
- ≈ 470 MW IT 30 June 2026
- Evidence scope
- Operator portfolio · CDC
- Evidence as-of date
- 2026-06-30
How to read this: The portfolio is included once in the operating reconciliation. Brooklyn accounts for the Victorian 130 MW; other named-site allocations remain incomplete. Primary ICT excludes the redundancy and losses in CDC’s earlier built-capacity measure. It is available capacity, not actual consumption.
Inspect the source
- CDC independent valuation, 30 June 2026 ↗
Infratil / CDC · checked 2026-09-22 · published 2026-07-06
PDF page 6 (printed page 5), Leasable Capacity Pipeline by Region, definition, operating rows and rounding footnote; page 5 (printed page 4), quarterly operating additions
Evidence trail
- CDC Marsden Park DC6: directory profile and specifications ↗
Data Center Map · checked 2026-09-11
Public listing 11310; location, overview, specs tabs. Address/location header and labelled technical specification rows.
- Social Impact Assessment – 105 and 113 Hollinsworth Road, Marsden Park State Significant Development (SSD-70889211 EIS appendix) ↗
NSW Planning Portal (Major Projects) · checked 2026-11-03 · published 2024-11-01
Title page and 'About Astrolabe Group'; dated 1 November 2024; Title page
- Marsden Park Data Centre (SSD-70889211) – NSW Planning Portal project page ↗
NSW Planning Portal · checked 2026-11-03 · published 2025-11-27
Project description and 'Project Details' (Decision Approved, Determination Date 27/11/2025); Project description and 'Project Details'
- CDC Marsden Park DC6: OpenStreetMap node 7103724776 ↗
OpenStreetMap contributors · checked 2026-11-03
Nominatim search result; node 7103724776; latitude -33.7226039, longitude 150.8365843. Checked 3 November 2026.
- Infratil Investor Day 2026 – CDC Update (16 September 2026) ↗
Infratil Limited · checked 2026-11-03 · published 2026-09-16
Slide 'Operating capacity has more than doubled over the last 18 months'; Slide 'Construction is progressing to meet FY27-29 deliveries'