CDC · Australia
CDC Kemps Creek KC1
Report an error or share evidence ↗
Also recorded as: CDC Data Centre Campus, Kemps Creek · SSD-133677993
Sydney, NSW · facility
- Facility type
- colocation
- Location evidence
- Approximate city location
- Research status
- Profile reviewed · 50% core-field coverage
Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.
Evidence by field
Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.
- Address Source checked
- CDC's Kemps Creek project page places the data centre in the industrial area at 845-901 Mamre Road; the NSW Planning Portal lists the campus application SSD-133677993. An earlier single-building filing was reported at 871-901 Mamre Road.Checked 2026-11-03 · CDC Data Centres ↗ · NSW Planning Portal ↗
- Coordinates Not found in checked sources
- No numbered address feature for 845-901 Mamre Road, Kemps Creek exists in OpenStreetMap. Approximate city position retained.Checked 2026-11-03 · CDC Data Centres ↗ · NSW Planning Portal ↗
- Status Source checked
- The campus application (six two-storey buildings, 1.4 GW total power consumption) shows 'Amend SEARs' status before environmental impact assessment; the earlier single 144 MW KC1 building filing appears to have been superseded. Planned, with no capacity accepted.Checked 2026-11-03 · NSW Planning Portal ↗ · Data Center Dynamics (DCD) ↗
845-901 Mamre Road, Kemps Creek, NSW
Checked 2026-11-03 · Map coordinates still to be verified
Open this address in maps ↗Capacity & development
Power basis not established
Directory reports Planned. No comparable IT capacity or commissioning date has been accepted from this listing.
Government certification
Certification not verified
No verified certification scope has been assigned to this record. Unknown does not mean uncertified.
What certification covers →Scope and context
- First listed from a public Data Center Map listing; identity, address and lifecycle have since been checked against the operator, planning and news sources cited on this record.
- Infratil's September 2026 update describes Kemps Creek as CDC's third Sydney campus, with land purchases settling in FY27-28.
Compute, workloads & commercial commitments
Site-specific workloads, GPU inventory and customer contracts are not established by the cited evidence. Electrical capacity and AI-ready specifications alone do not establish these details.
Related operator-wide evidence
These disclosures describe the operator’s portfolio. They are not assigned to this facility or included in its power totals.
CDC reports a 3.9 GW leasable ANZ pipeline
September 2026 investor update reports 3.9 GW leasable pipeline as at 30 June 2026. Earlier 1.7 GW leasable capacity corresponded to a 2.5 GW built capacity pipeline. The definitions differ and cannot be summed.
- Total leasable pipeline
- 3,900 MW leasable 2026-06-30
- Evidence scope
- Operator portfolio · CDC
- Evidence as-of date
- 2026-06-30
How to read this: Includes existing operating and future capacity across Australia and New Zealand. It is not additional pipeline or site-allocated IT capacity and is not additive to facility totals.
Inspect the source
- CDC Infratil investor update, 16 September 2026 ↗
CDC / Infratil · checked 2026-09-22 · published 2026-09-16
Slides: CDC Group snapshot; Then and now; Operating capacity has more than doubled; Construction is progressing; footnotes defining pipeline
CDC Australian operating ICT capacity: approximately 470 MW
CDC reports operating primary ICT capacity of approximately 120 MW in the ACT, 220 MW in NSW and 130 MW in Victoria at 30 June 2026. The regional figures are rounded to the nearest 10 MW.
- Operating primary ICT capacity
- ≈ 470 MW IT 30 June 2026
- Evidence scope
- Operator portfolio · CDC
- Evidence as-of date
- 2026-06-30
How to read this: The portfolio is included once in the operating reconciliation. Brooklyn accounts for the Victorian 130 MW; other named-site allocations remain incomplete. Primary ICT excludes the redundancy and losses in CDC’s earlier built-capacity measure. It is available capacity, not actual consumption.
Inspect the source
- CDC independent valuation, 30 June 2026 ↗
Infratil / CDC · checked 2026-09-22 · published 2026-07-06
PDF page 6 (printed page 5), Leasable Capacity Pipeline by Region, definition, operating rows and rounding footnote; page 5 (printed page 4), quarterly operating additions
Evidence trail
- CDC Kemps Creek KC1: directory profile and specifications ↗
Data Center Map · checked 2026-09-11
Public listing 18770; location, overview, specs tabs. Address/location header and labelled technical specification rows.
- Kemps Creek | CDC ↗
CDC Data Centres · checked 2026-11-03
Section 'Project map' (first paragraph) and 'About the project'
- CDC Data Centre Campus, Kemps Creek (SSD-133677993) – NSW Planning Portal project page ↗
NSW Planning Portal · checked 2026-11-03
Project description and 'Current Status' banner (the earlier URL .../kc1-data-centre-kemps-creek redirects here)
- Australia's CDC files for data center in Kemps Creek, Sydney ↗
Data Center Dynamics (DCD) · checked 2026-11-03
Lead paragraph and subheading 'Company plans a single 144MW building'
- Infratil Investor Day 2026 – CDC Update (16 September 2026) ↗
Infratil Limited · checked 2026-11-03 · published 2026-09-16
Slide 'Operating capacity has more than doubled over the last 18 months'; Slide 'Construction is progressing to meet FY27-29 deliveries'
- Natural Earth populated places, 1:10m ↗
Natural Earth · checked 2026-09-10
Australia and New Zealand populated-place features