Quinbrook · Australia
Supernode data centre campus
Report an error or share evidence ↗
Brisbane, QLD · campus
- Facility type
- hyperscale
- Location evidence
- Approximate city location
- Research status
- Profile reviewed · 63% core-field coverage
Core-field coverage counts eight basic fields available in the Atlas. It is not an accuracy score or a measure of technical specification completeness. Individual evidence checks appear below.
Evidence by field
Evidence status applies to the named field and cited sources. “Not found” means those sources do not establish the fact; it does not establish absence.
- Capacity Source checked
- Explicit 500 MW-IT proposed design envelope; distinct from 780 MW BESS.Checked 2026-09-22 · Quinbrook ↗
- Status Source checked
- Data-centre stages remain proposed; battery stage operations do not establish data-centre operation.Checked 2026-09-22 · Quinbrook ↗
Capacity & development
Power for servers, GPUs, storage & networking (IT power)
Proposed 500 MW IT data-centre precinct at full build. This is a potential development envelope with no committed delivery date. Separate battery storage MW and commercial-operation milestones are excluded.
Proposed or approved design capacity. Included in the planning inventory, not a dated delivery forecast or a claim of committed supply.
Government certification
Certification not verified
No verified certification scope has been assigned to this record. Unknown does not mean uncertified.
What certification covers →Scope and context
- Planned data centre development at Brendale is distinct from the campus battery project. Operational battery stages do not establish operating data centre capacity.
- Technical details reported by Data Center Map are shown separately from the Atlas's primary-source observations.
- Rechecked 22 September 2026: the developer still explicitly identifies 500 MW IT potential data-centre capacity. Included as a proposed IT design envelope under the same treatment as other conditional full-build proposals.
Compute, workloads & commercial commitments
Site-specific workloads, GPU inventory and customer contracts are not established by the cited evidence. Electrical capacity and AI-ready specifications alone do not establish these details.
Explore demand, compute types and commitments →Evidence trail
- Supernode digital and energy infrastructure project ↗
Quinbrook · checked 2026-09-11
2026+ stages 4 and 5; 500 MW-IT potential capacity
- Supernode: directory profile and specifications ↗
Data Center Map · checked 2026-09-11
Public listing 11264; location, overview, specs tabs. Address/location header and labelled technical specification rows.
- Supernode — Quinbrook ↗
Quinbrook · checked 2026-09-22
Project History: 2026+ stages 4 and 5; 500 MW-IT potential capacity tile; Battery-backed, renewable-ready
- Natural Earth populated places, 1:10m ↗
Natural Earth · checked 2026-09-10
Australia and New Zealand populated-place features